Construction Progress

ACHIEVEMENTS:
üContract Negotiations
üCity Council Approval 22-JUL
üPermitting Finalized
üSWPPP Permit Complete
üTemporary Fire Station Trailer Delivered
üObtain Construction Permit
üKick-Off Meeting 01-AUG
üIssue Notice to Proceed 01-AUG
üCORE Construction Mobilization 04-AUG
üTree Protection, Clearing and Grubbing
|
NEXT STEPS:
qTemp Station Submittals 11-AUG
qProcure Sprung Structure
qSprung Structure August –November
qTemp Station Flex base
qTemp Station Trailer MEP
qSprung Foundation
qInstall Sprung Structure
qInstall OH Doors
qMoisture Conditioning Building Pad 08-SEP
qStart Sanitary Sewer Install 22-SEP
qStart Storm Sewer Install 22-SEP
qPier Survey Followed by Drilling 23-SEP
|
Share Construction Progress on Facebook
Share Construction Progress on Twitter
Share Construction Progress on Linkedin
Email Construction Progress link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends