Construction Progress

ACHIEVEMENTS:

üTree Protection, Clearing and Grubbing
üGrading
üMoisture Conditioning for Pad
üSecurity Fence Complete
üPier Survey
ü50% Piers Complete
üSprung Structure Procured
üUtility Layout for Temp

NEXT STEPS:

qProject Submittals Ongoing
q50% Pad Left (House, Storm Shelter, Dumpster Pad and Generator Pad Piers)
qStart Sanitary Sewer Install
qStart Storm Sewer Install
qGrade Beam Forms and Excavation Perimeter
qGrade Beam Forms and Excavation Interior
qGrade Beam Forms and Excavation House
qInstall RCP and Boxes – Area South
qTemp Station Submittals
qTemp Station Flex base
qTemp Station Trailer MEP
qInstall Domestic Water Line (In-Process)
qSprung Foundation
qInstall Sprung Structure
qInstall OH Doors
qInstall Electric Underground Feed from Transformer
qInstall Sanitary Temp (In-Process)
qInstall Concrete Pads for Generator and Riser Room