Construction Progress
Fire Station #5
|
ACHIEVEMENTS:
üSprung Structure Grading
üTemp Station Submittals
üDomestic Water Line
üUG Power Line
üSanitary Sewer Line
üFire 5 Erosion Control/Watershed Inspection
|
NEXT STEPS:
qTemp Station Flex base
qSprung Foundation
qInstall Sprung Structure
qInstall OH Doors
qInstall Electric Underground Feed from Transformer
qInstall Sanitary Temp (In-Process)
qInstall Concrete Pads for Generator and Riser Room
qTemp Station Interior MEP
|
Fire Station #6
|
ACHIEVEMENTS:
ü100% Piers Complete
üGrade Beams (Apparatus Bay) Complete
üGrade Beams (Operations Side) Formed
üSouth Storm Sewer 50%
|
NEXT STEPS:
qPour Grade Beams (Operations Side)
qStart Storm Sewer Install
qExcavate & Install Water Line
qExcavate & Install Storm Line
qExcavate & Install Gas Line
qExcavate & Install Power Line
qUnderground MEP (Bay and Ops)
qPour Slab
|
Share Construction Progress on Facebook
Share Construction Progress on Twitter
Share Construction Progress on Linkedin
Email Construction Progress link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends