Construction Progress

Fire Station #5

ACHIEVEMENTS:

üSprung Structure Grading
üTemp Station Submittals
üDomestic Water Line
üUG Power Line
üSanitary Sewer Line
üFire 5 Erosion Control/Watershed Inspection

NEXT STEPS:

qTemp Station Flex base
qSprung Foundation
qInstall Sprung Structure
qInstall OH Doors
qInstall Electric Underground Feed from Transformer
qInstall Sanitary Temp (In-Process)
qInstall Concrete Pads for Generator and Riser Room
qTemp Station Interior MEP

Fire Station #6

ACHIEVEMENTS:

ü100% Piers Complete
üGrade Beams (Apparatus Bay) Complete
üGrade Beams (Operations Side) Formed
üSouth Storm Sewer 50%

NEXT STEPS:

qPour Grade Beams (Operations Side)
qStart Storm Sewer Install
qExcavate & Install Water Line
qExcavate & Install Storm Line
qExcavate & Install Gas Line
qExcavate & Install Power Line
qUnderground MEP (Bay and Ops)
qPour Slab
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link