Construction Progress
Fire Station #5
|
ACHIEVEMENTS:
- Sprung Structure Grading
- Temp Station Submittals
- Domestic Water Line
- UG Power Line
- Sanitary Sewer Line
- Fire 5 Erosion Control/Watershed Inspection
- Temp Station Flex base
- Sprung Foundation
- Install Sprung Structure
|
NEXT STEPS:
- Install OH Doors
- Install Electric Underground Feed from Transformer
- Install Sanitary Temp (In-Process)
- Install Concrete Pads for Generator and Riser Room
- Temp Station Interior MEP
|
Fire Station #6
|
ACHIEVEMENTS:
- 100% Piers Complete
- Grade Beams (Apparatus Bay) Complete
- Grade Beams (Operations Side) Formed
- South Storm Sewer 50%
- Pour Grade Beams (Operations Side)
- Start Storm Sewer Install
|
NEXT STEPS:
- Excavate & Install Water Line
- Excavate & Install Storm Line
- Excavate & Install Gas Line
- Excavate & Install Power Line
- Underground MEP (Bay and Ops)
- Pour Slab
|
Share Construction Progress on Facebook
Share Construction Progress on Linkedin
Email Construction Progress link
Thank you
for your contribution!
Help us reach out to more people in the community
Share this with family and friends
No thanks
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends