ACHIEVEMENTS:

üMaterial Testing
üFinal Scoring of CMAR and Selection
üCMAR Preconstruction Negotiation
ü100% Schematic Design complete

NEXT STEPS:

qPrecon CMAR GMP - City Council Date Pending
qTerracon Engineering Services Scope and Contract
q100% Extreme Modular Building Construction Doc.
q100% Design Documents
q50% Construction Documents
q100% CD Issued for Permitting and Bidding
qExtreme Modular Building Delivery Dec-Jan
qGMP to City Council Dec-Jan