Design Phase


ACHIEVEMENTS:

üCMAR Preconstruction Negotiation
ü100% Schematic Design complete
ü100% Design Documents 20-Aug
üStorm Shelter Proposal Recieved

NEXT STEPS:

qTerracon Engineering Scope and Contract
q100% DD Review by City
qInitial Estimates (Mid-Sept)
q50% Construction Documents 01-Oct
q100% CD’s Complete 29-Nov
q100% CD’s City Review (6 weeks)