Design Phase

ACHIEVEMENTS:

  • 100% Design Documents

  • 100% Extreme Modular Building Design Document

  • Early Estimate Received from CMAR and Reviewed by City Stakeholders

  • 50% CD’s 01-Oct

  • Preconstruction efforts/Site Investigation

  • FF&E/IT Budgeting Meetings

  • EMB Foundation Design

  • CoD Capital Projects Partnering Session for FS5&6 13-Sep


NEXT STEPS:

  • Terracon Engineering Services Scope and Contract to CC 22-Oct

  • 50% Construction Documents (City Review)

  • 50% Estimates

  • 90% Construction Documents 12-Nov

  • Extreme Modular Building Construction Documents to be Approved by State

  • 100% CD Issued for Permitting and Bidding 17-Dec

  • Extreme Modular Building Construction

  • GMP-01 to CC 22-NOV (EMB/Early Site Work/Gensets)

  • Project Kickoff 31-Oct

  • Early Permitting

  • Acquire Storm Shelter Consulting Service

  • Art Package to CoD Art Committee