Design Phase
ACHIEVEMENTS:
ü50% Construction Documents (City Review)
ü100% Extreme Modular Building Design Document
üEarly Estimate Received from CMAR
üIT Page Turns and Budget Development (DFS5&EMB)
üFF&E Budget Development (DFS5&EMB)
üArt Package Returned from Art Committee
üStorm Shelter Consultant
|
NEXT STEPS:
qTerracon Engineering Services Scope and Contract to CC 19-NOV
q50% Budget Review with CMAR (Meeting 07-NOV)
q90% Construction Documents 12-Nov
qExtreme Modular Building Construction Documents to be Approved by State
q100% CD Issued for Permitting and Bidding 17-Dec
qExtreme Modular Building Construction
qGMP-01 to Re-Bid 06-NOV
qArt Package back to CoD Art Committee
|