Design Phase

ACHIEVEMENTS:
ü50% Construction Documents (City Review)
ü100% Extreme Modular Building Design Document
üEarly Estimate Received from CMAR and Reviewed by City Stakeholders
üIT Page Turns and Budget Development (DFS5&EMB)
üFF&E Budget Development (DFS5&EMB)
üArt Package Returned from Art Committee with Comments
üStorm Shelter Consultant
ü50% Budget Review with CMAR
ü90% Construction Documents
üGMP-01 2nd Round of Bids Closed
NEXT STEPS:
qGMP-01 to City for Review 02-DEC
qEMB Foundation and App Bay Design Changes
qTerracon Engineering Services Scope and Contract to CC 17-DEC
qExtreme Modular Building Construction Documents to be Approved by State
qGMP-01 to CC for Approval Possibly 17-DEC
q100% CD Issued for Permitting and Bidding 17-Dec
qExtreme Modular Building Construction
qArt Package back to CoD Art Committee
qNext Estimates (Early December) to Include Changes in Masonry, Roof, and OTS Doors
Share Design Phase on Facebook
Share Design Phase on Twitter
Share Design Phase on Linkedin
Email Design Phase link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends