Desing/Procurement Phase
ACHIEVEMENTS: üCORE Bid Package Submitted to City Purchasing for Review
üTerracon Engineering Services Scope and Contract Approved by City Council
ü100% Construction Documents Submitted for Permitting
üFF&E Budget Development (DFS6)
üArt Package Submitted for Bids
üStorm Shelter Consultant
üFiber/DME Resolution
üArt Package Submitted for Bids
üStorm Shelter Consultant
|
NEXT STEPS: qAdvertise for Bids 5-MAR
qPrebid Meeting 12-MAR
qFinalize Utilities for Temp Station
qPlan Permit Review (In Progress)
qGMP Creation (April)
qGMP to Council (April-May)
qConstruction (June)
|