Desing/Procurement Phase

ACHIEVEMENTS:

üReceived Bids 25-MAR
üPre-Bid Meeting 12-MAR
üAdvertise for Bids 5-MAR
üModular IT Equipment Plan
üCORE Bid Package Submitted to City Purchasing for Review
üTerracon Engineering Services Scope and Contract Approved by City Council
ü100% Construction Documents Submitted for Permitting
üFF&E Budget Development (DFS5&Modular)
üArt Package Submitted for Bids

NEXT STEPS:

qSprung App Bay and Trailer Purchase and Transportation
qFinalize Utilities for Temp Station
qPlan Permit Review (In Progress)
qArt Bids Due 31-MAR
qGMP to City for Review 15-APR
qGMP to Council 5-May
qConstruction (June)