Desing/Procurement Phase
ACHIEVEMENTS:
üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
üPrebid Completed
üGMP Creation
üILA Pflugerville/Denton for Temp Trailer Executed
|
NEXT STEPS:
qFinalize Permitting
qGMP to the CoD 29-APR Negotiations
qGMP to Purchasing for CC Meeting Agenda 5-MAY
qGMP to CC 03-Jun
qGMP NTP 20-Jun (Temp Facility)
qProcurement – Switchgear, Panels, Generator and Structural Steel
qFire Station 5 Construction Start 07-NOV
|