Desing/Procurement Phase
ACHIEVEMENTS:
üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
üPrebid Completed
üZoning Committee Approval
üAll Permitting Documents Submitted to City of Denton for Both Temp and Permanent
üPrebid Completed
üGMP Creation
üILA Pflugerville/Denton for Temp Trailer Executed
üPermitting Finalized
|
NEXT STEPS:
qSubmit Landscaping and Civil for Permitting
qStipulated Sum GMP Negotiations
qFinalized GMP to City 13-JUN
qGMP to CC 15-JUL
qNTP 16-JUL
|