Design/Procurement Phase

ACHIEVEMENTS:

üContract Negotiations
üCity Council Approval 22-JUL
üPermitting Finalized
üSWPPP Permit Complete
üTemporary Fire Station Trailer Delivered

NEXT STEPS:

qObtain Construction Permit
qKick-Off Meeting 01-AUG
qIssue Notice to Proceed 01-AUG
qCORE Construction Mobilization 04-AUG
qTemp Station Submittals 11-AUG
qTemp Station Construction 12-AUG to 30-OCT
qSprung Strructure August -November
qGrading 04-AUG