Construction Starting
Starting March 13, 2024 the pavilion near the basketball court will be closed as it will undergo demolition to install a new pavilion.
The current timeline for this project is the following and is subject to change pending weather or permitting delays.
- Pavilion Demolition & Construction: March 13 - April 12
- Concrete sidewalk addition to the softball fields: March 18- March 29
- Pergola addition to the American Legion Hall: March 25 - May 3
Share Construction Starting on Facebook
Share Construction Starting on Twitter
Share Construction Starting on Linkedin
Email Construction Starting link
Construction is complete.