Hickory Creek Road Phase 2 (West)

Share on Facebook Share on Twitter Share on Linkedin Email this link

Consultation has concluded

The Hickory Creek Road Phase 2 (West) project is from west of Teasley Lane to Riverpass Road/FM 2499. The project will improve mobility and safety in the area by expanding the existing roadway to include four main lanes, a median, storm drain system, a bridge, and turn lanes. If necessary, there will be room to construct two additional inside lanes (one in each direction) in the future.

In addition to the new roadway, the project includes 4,000 linear feet of storm drain (18-48 inches in diameter). A portion of the 10-foot sidewalk was constructed last summer and is excluded from the scope of this project. The drainage system that will be constructed is designed to provide capacity for the 100-year storm event. In addition, a new bridge will be constructed next to the existing bridge over Fletcher Branch to carry the Eastbound traffic.

Project Status

The Hickory Creek Road Phase 2 (West) project is from west of Teasley Lane to Riverpass Road/FM 2499. The project will improve mobility and safety in the area by expanding the existing roadway to include four main lanes, a median, storm drain system, a bridge, and turn lanes. If necessary, there will be room to construct two additional inside lanes (one in each direction) in the future.

In addition to the new roadway, the project includes 4,000 linear feet of storm drain (18-48 inches in diameter). A portion of the 10-foot sidewalk was constructed last summer and is excluded from the scope of this project. The drainage system that will be constructed is designed to provide capacity for the 100-year storm event. In addition, a new bridge will be constructed next to the existing bridge over Fletcher Branch to carry the Eastbound traffic.

Project Status

Consultation has concluded
  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Crews are completing the striping and sign installation on the Hickory Creek Road Phase 2 (West) project. Crews will begin next week on finishing the final punch list items to complete the project. The main lanes of traffic will be open but expect small lane closure patterns as the final items for completion are preformed. If you have any questions please use the Ask The Project Manager with this project page, or at Dustin.Draper@cityofdenton.com.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The Hickory Creek Road Phase 2 (West) project has added a median break at Livingston. The median break work is scheduled to start this week and will allow a left turn in for traffic from the east bound lanes, as well as allowing a left out from Livingston to the east toward Teasley. The additional scope for the project has a estimated completion of December 2022.

  • Hickory Creek PH 2 (West) Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Sidewalk as well as curb & gutter installation is being performed on the project currently on the east end of the project. The project site mowing is scheduled to start tomorrow. During these times please use cation when driving in the project area. To stay informed on updates to the project you can visit us back here on the Discuss Denton project page.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Next week sections of the projects will begin to have pavement markings installed. We ask that you please use caution while driving in the project area during this time. If you have any questions please email us at the project email address.

  • Project Lane Demo Video Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    https://youtu.be/nnjXdRD6aRM

  • Hickory Creek Road Phase 2 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The current completion date for Hickory Creek PH 2 is Quarter 3 of 2022. The date had to be pushed out due to utility conflicts found in the field in December 2021. City staff has worked with the contractor to resolve the conflicts to complete construction. The contractor’s crew is currently scheduled to complete site maintenance issues with grass areas by the end of this week. The project in the coming weeks will be swapping traffic patterns so please stay alert to changing road conditions.

  • Project Completion Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The expected project completion is Q2 2022. Crews are completing final construction and cleanup activities along the project route.

  • Project Completion Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Currently, crews are laying drainage and water lines along the project route. As a result of utility relocation delays, the new anticipated construction completion date is Q2 2022.

  • Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Construction continues to progress on this project. Motorists traveling in the area are reminded to use caution and adhere to all posted construction signage.

  • Water and Drainage Line Installation

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Crews are currently laying drainage and water lines on Hickory Creek Road from Teasley Lane to Riverpass Drive. Multiple utility relocations and project scope updates have impacted the anticipated construction timeline. The new anticipated construction end date is Q1 2022.