Hickory Creek Road Phase 2 (West)

Share Hickory Creek Road Phase 2 (West) on Facebook Share Hickory Creek Road Phase 2 (West) on Twitter Share Hickory Creek Road Phase 2 (West) on Linkedin Email Hickory Creek Road Phase 2 (West) link

Consultation has concluded

The Hickory Creek Road Phase 2 (West) project is from west of Teasley Lane to Riverpass Road/FM 2499. The project will improve mobility and safety in the area by expanding the existing roadway to include four main lanes, a median, storm drain system, a bridge, and turn lanes. If necessary, there will be room to construct two additional inside lanes (one in each direction) in the future.

In addition to the new roadway, the project includes 4,000 linear feet of storm drain (18-48 inches in diameter). A portion of the 10-foot sidewalk was constructed last summer and is excluded from the scope of this project. The drainage system that will be constructed is designed to provide capacity for the 100-year storm event. In addition, a new bridge will be constructed next to the existing bridge over Fletcher Branch to carry the Eastbound traffic.

Project Status

The Hickory Creek Road Phase 2 (West) project is from west of Teasley Lane to Riverpass Road/FM 2499. The project will improve mobility and safety in the area by expanding the existing roadway to include four main lanes, a median, storm drain system, a bridge, and turn lanes. If necessary, there will be room to construct two additional inside lanes (one in each direction) in the future.

In addition to the new roadway, the project includes 4,000 linear feet of storm drain (18-48 inches in diameter). A portion of the 10-foot sidewalk was constructed last summer and is excluded from the scope of this project. The drainage system that will be constructed is designed to provide capacity for the 100-year storm event. In addition, a new bridge will be constructed next to the existing bridge over Fletcher Branch to carry the Eastbound traffic.

Project Status

Consultation has concluded
  • Elementary School Pedestrian Access Update

    Share Elementary School Pedestrian Access Update on Facebook Share Elementary School Pedestrian Access Update on Twitter Share Elementary School Pedestrian Access Update on Linkedin Email Elementary School Pedestrian Access Update link
    supporting image
    To help provide a temporary walking path on the north side of Hickory Creek Road (across from McNair Elementary), City staff have worked with the contractor to place gravel on the existing footpath for pedestrians to use. The gravel has been placed to produce a more weather resistant walking surface for the pedestrians, particularly the students at McNair Elementary, to use as they walk between Montecito Drive and the existing concrete sidewalk west of Waterside Place. Pedestrians are asked to use this route rather than walk in the street to avoid construction activities.

    Pedestrians are reminded to be aware of nearby construction equipment and other areas that are fenced off for safety.
  • Temporary Concrete Traffic Barriers

    Share Temporary Concrete Traffic Barriers on Facebook Share Temporary Concrete Traffic Barriers on Twitter Share Temporary Concrete Traffic Barriers on Linkedin Email Temporary Concrete Traffic Barriers link
    supporting image
    City staff has reviewed several safety options and are recommending the installation of temporary concrete barriers along the edge of the existing curb adjacent to the school playground. These barriers will improve safety and help in deflecting vehicles that may inadvertently veer off the road towards the school playground. Staff has requested cost estimates for the barriers and is currently waiting for the contractor to provide them. Staff plans on installing the barriers as soon as possible and will be communicating this plan with Denton ISD officials so that information can be communicated to parents.
    In the long term, as the construction comes to a completion and the road is fully widened, staff will work to design a permanent solution and implement it as a component of the widening project. Staff will continually work with DISD staff to ensure they are fully apprised of these activities.
  • Temporary Lane Closure Rescheduled

    Share Temporary Lane Closure Rescheduled on Facebook Share Temporary Lane Closure Rescheduled on Twitter Share Temporary Lane Closure Rescheduled on Linkedin Email Temporary Lane Closure Rescheduled link
    supporting image

    Due to inclement weather, the temporary lane closure have been postponed. The updated schedule will be as followed: Weather permitting, Wednesday, Feb. 12 through Friday, Feb. 14, from 8am to 8pm, Hickory Creek Road from Westside Place to Montecito Drive will have temporary lane closures and traffic control flaggers in place.

    Wednesday, Feb. 19 through Friday, Feb. 28, Montecito Drive from Hickory Creek Road to Buena Vista Drive will be temporarily closed to thru traffic.

  • Temporary Lane Closures and Traffic Control Flaggers

    Share Temporary Lane Closures and Traffic Control Flaggers on Facebook Share Temporary Lane Closures and Traffic Control Flaggers on Twitter Share Temporary Lane Closures and Traffic Control Flaggers on Linkedin Email Temporary Lane Closures and Traffic Control Flaggers link
    supporting image

    Weather permitting, Tuesday, Feb. 4 from 8am to 9pm, Hickory Creek Road from Westside Place to Montecito Drive will have temporary lane closures and traffic control flaggers in place. During this time, crews will be installing a storm drain pipe as part of the active road widening project. Crews expect the installation to be completed, and the lanes reopened on or before the end of day Wednesday, Feb. 5.

    In addition, Monday, Feb. 10 through Monday, Feb. 24, Montecito Drive from Hickory Creek Road to Buena Vista Drive will be temporary closed to thru traffic. This temporary closure will allow crews to safely install a new storm drain pipe. Crews will make necessary accommodations to ensure residents maintain access at all times during construction.

    Signage is posted to alert motorists of the scheduled temporary lane closures and traffic control flaggers. Delays and backups are possible so motorists are reminded to use caution when traveling in the area and seek an alternate route if possible.