Project Status Update

The Hickory Creek Road Phase 3 project is currently pouring bridge columns, filling in the abutments, pouring bridge caps, and constructing temporary haul roads. We ask that as this construction is underway please use caution and obey all warning signs related to the project. Denton County is currently completing the construction of HIlltop Road that ties into the Hickory Creek Rd Ph 3 project, and the two way traffic of HIlltop Rd is scheduled to be restored in the next two weeks. For your safety please avoid entering into the active construction areas of the project unless you are a landowner or a resident within the road closure area. If you have any questions or concerns contact Staff at Dustin.Draper@cityofdenton.com.