Summer Fun on Hickory Creek Road

It's HOT and Sinacola is BUSY. Construction has been underway on Hickory Creek Road and progress is being made! Focus has been on the WEST End of Hickory Creek Road at FM 1830 to get Hilltop Road opened as soon as possible. But there's been work EVERYWHERE on the project!


PROGRESS - Activities include (and not limited to):

- Site clearing and grading and re-mobilization (COMPLETE)

- Installation of drainage structures and creek crossing

- New Right Turn Lane at FM 1830

- Bridge Work (the Caps are Coming!!)

- New Hilltop Tie-in (see pix below - Concrete is coming 8/1/25)


SCHEDULE

WHOLE Project - Project has a target of completion end of 2026.

HILLTOP ROAD Connection - Reopening - target is End of September 2025


PICTURES

NEW Hilltop (looking North). Bye-Bye dirt road, hello Concrete!!!


NEW Hilltop (looking South)


Hickory Creek Road (looking west)

This section of road will be asphalt/hot mix as it ties back to FM 1830.

New Bridge Work!

The columns are getting their Caps!!