The Landfill Entrance Improvements that will be completed include:

  • Installation, rental and removal of a temporary scale facility
  • Demolition of pavements, sidewalks, utilities, scales, and foundations
  • Installation of concrete pavements
  • Installation of scale foundations and ramps
  • Installation of new scales
  • Remodel of the existing scale house


The Landfill Entrance Improvements that will be completed include:

  • Installation, rental and removal of a temporary scale facility
  • Demolition of pavements, sidewalks, utilities, scales, and foundations
  • Installation of concrete pavements
  • Installation of scale foundations and ramps
  • Installation of new scales
  • Remodel of the existing scale house


  • Project Update - July 2024

    Share Project Update - July 2024 on Facebook Share Project Update - July 2024 on Twitter Share Project Update - July 2024 on Linkedin Email Project Update - July 2024 link
    supporting image

    We will be kicking off construction soon. We will begin by setting up a temporary building for City Staff that manage the scales and by installing temporary scales.

    There will be a new traffic pattern once the temporary facilities are in place. Click "Photos" on the right of the page for an easier to see depiction.

  • Project Update - June 2024

    Share Project Update - June 2024 on Facebook Share Project Update - June 2024 on Twitter Share Project Update - June 2024 on Linkedin Email Project Update - June 2024 link
    supporting image

    We are pleased to announce that City Council has approved the construction award to Gage & Cade Construction. Next step is to set up a kickoff meeting and get the improvements underway.

  • Project Update - April 2024

    Share Project Update - April 2024 on Facebook Share Project Update - April 2024 on Twitter Share Project Update - April 2024 on Linkedin Email Project Update - April 2024 link

    Contract negotiations are underway with a General Contractor and once finalized will go before City Council for approval.

  • Project Update - February 2024

    Share Project Update - February 2024 on Facebook Share Project Update - February 2024 on Twitter Share Project Update - February 2024 on Linkedin Email Project Update - February 2024 link

    The solicitation request for a General Contractor has been published. Bids are due March 20th, via ionwave or in person by 1:00pm. All questions should be directed to purchasing department while the solicitation is open. Bids will be read immediately following at 1:30pm.

  • Project Updates

    Share Project Updates on Facebook Share Project Updates on Twitter Share Project Updates on Linkedin Email Project Updates link

    The project design is 100% complete. The invitation for bid will be released to registered vendors in Quarter 1 2024.

    The schedule will be published once a general contractor is selected.