Mayhill Road

Share on Facebook Share on Twitter Share on Linkedin Email this link

As Denton has grown over the years, so has the congestion on Mayhill Road. The City has been working to expand Mayhill from a two-lane undivided roadway to a four-lane divided roadway to accommodate traffic. Once complete, Mayhill Road will be able to handle the continued growth in the area and serve as an alternate route to Loop 288.

Phase 2 (Colorado to North of Quail Creek) will include extending Mayhill Road from Colorado Boulevard to the existing 4-lane divided roadway and eliminate the at-grade crossing at DCTA/Edwards. This phase will also include the installation of a traffic signal at the Mayhill Road and Colorado Boulevard intersection, side paths and trails.

Project Status

Phase 2 (Colorado to North of Quail Creek)

Phase 1 (I-35E to US 380)

As Denton has grown over the years, so has the congestion on Mayhill Road. The City has been working to expand Mayhill from a two-lane undivided roadway to a four-lane divided roadway to accommodate traffic. Once complete, Mayhill Road will be able to handle the continued growth in the area and serve as an alternate route to Loop 288.

Phase 2 (Colorado to North of Quail Creek) will include extending Mayhill Road from Colorado Boulevard to the existing 4-lane divided roadway and eliminate the at-grade crossing at DCTA/Edwards. This phase will also include the installation of a traffic signal at the Mayhill Road and Colorado Boulevard intersection, side paths and trails.

Project Status

Phase 2 (Colorado to North of Quail Creek)

Phase 1 (I-35E to US 380)

  • Phase 1 Complete

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Phase I of the Mayhill Road project is now substantially complete. This project expanded Mayhill Road (US 380 to north of Quail Creek Road) from a two-lane road to a four-lane divided road, added new water, sewer lines, and drainage structures. Learn more from the project manager in the newsbreak below.


  • Phase 2 Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Phase 2 of the Mayhill project is currently in the final stage of design with right-of-way acquisitions underway, and is tentatively scheduled to begin construction in Q2 2021. This phase of the project will include a 4-lane expansion towards Colorado Boulevard. This phase will also address congestion issues and include a bridge over the DCTA Rail to eliminate the at-grade intersection with the DCTA Railroad.

  • Phase 2 Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    While construction activities for Phase 2 of the Mayhill project are not scheduled to begin until Q2 2021, staff are coordinating with DCTA for bridge approval, completing real estate activities, and addressing regional detention along the project route. Phase 2 will progress to the bid, advertise, and award phase and construction activities will follow.