Construction Update Dec 2025

Force Main has been installed and finishing the ARV manholes.

Gravity Sewer has majority of the bores started/completed and line installation has begun. A few conflicts have come up causing some delays with construction and unexpected traffic pattern changes to come. Traffic will be affected at the TA and Love's Truck Stops at US-77/Barthold Rd and I-35 Frontage Road.

Lift Station site has been opened up to form the structures. Additional crew has been on site to speed this up due to a department change that delayed the start of the lift station. Also, the crew to bore under I-35 is returning to complete the 48" bore for the gravity line to lift station.