Mistywood Lane and Chebi Lane Construction

Construction for the MCFC project will be completed in phases to ensure safety, and access is maintained for motorists and residents in the area. The Mistywood Lane and Chebi Lane street segments will be completed first, followed by the Freedom Lane and Craig Lane street segments. Below are the traffic impacts and construction schedule for the first phase of construction. The second phase of construction is expected to begin in the fall, and residents will be provided with traffic impacts and a construction schedule in advance of construction beginning.

Here’s what to expect with the first phase of construction at Mistywood Lane and Chebi Lane:
Weather permitting, Monday, June 21 through Thursday, Aug. 19, the Eastbound lane of Chebi Lane from Old North Road to Freedom Lane and the Westbound lane of Mistywood between Old North Road and the cul-de sac will be closed. Traffic will be one-way Westbound on Chebi and one-way Eastbound on Mistywood with established detours. The traffic pattern will be shifted on Thursday, Aug. 19 through Friday, Sept. 10 with one-way traffic Westbound on Chebi Lane and one-way traffic Eastbound on Mistywood Lane. Message boards and traffic control signage is now in place to notify community members and motorists of the upcoming construction and impacts to traffic. Access will be maintained for local residents and property owners throughout the temporary lane closures.

Share on Facebook Share on Twitter Share on Linkedin Email this link

This project is complete. 

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>