The Contractor successfully tied in the new Northwest Water Transmission Line at (3) key locations. Coordination between the City of Krum, City of Sanger, the Water Department and the Contractor to accomplish the task at hand.
Share The Construction Project is 80% complete. on Facebook
Share The Construction Project is 80% complete. on Linkedin
Email The Construction Project is 80% complete. link
Mountain Cascade of Texas continues to install the transmission water line is now 80% complete with the project.
Share First Coordination Meeting to discuss water shutdowns and tie-ins held this week. on Facebook
Share First Coordination Meeting to discuss water shutdowns and tie-ins held this week. on Linkedin
Email First Coordination Meeting to discuss water shutdowns and tie-ins held this week. link
Consultant Engineer held the first coordination meeting to discuss the upcoming water shutdowns and tie-ins affecting the City of Krum and City of Sanger feeds.
Share The installation of the main distribution waterline continues. on Facebook
Share The installation of the main distribution waterline continues. on Linkedin
Email The installation of the main distribution waterline continues. link
The Contractor continues to install the 36-inch water line. The project is now approximately 60% complete.
Share Contractor is installing the main distribution line. on Facebook
Share Contractor is installing the main distribution line. on Linkedin
Email Contractor is installing the main distribution line. link
The Contractor is in the process of installing the main distribution line along Loop 288 & US 77. The project is 30% complete.
Share Contractor has installed Water Line D on Facebook
Share Contractor has installed Water Line D on Linkedin
Email Contractor has installed Water Line D link
The Contractor has completed installing Water Line D. Water Line D is 16-inch diameter pipe and 2,250 linear feet in length and made of ductile iron.
Share Contractor to Mobilize on Facebook
Share Contractor to Mobilize on Linkedin
Email Contractor to Mobilize link
On March 27, 2023, the Contractor, Mountain Cascade of Texas, LLC, will begin to mobilize into the work area. Contractor will begin the construction staking, setup erosion control and setup temporary fencing.
Share Contract Award on Facebook
Share Contract Award on Linkedin
Email Contract Award link
On December 13, 2022, The City of Denton awarded a contract to Mountain Cascade of Texas, LLC to construct the Northwest Water Transmission Main Project.