Update 7/14/2023
City crews have completed the mill and overlay of Cordero Ct. While milling and overlaying the west side of Vista Verde Ct., crews encountered subgrade issues that required a partial reconstruction of the road. This caused the timeline to be pushed back a few weeks.
Glendora Ct. was scheduled for a full reconstruction and is currently in the process of having curb and gutter, drive approaches, and sidewalk poured. We anticipate all concrete being poured by 7/21/2023, barring any weather setbacks. Following concrete work, the existing pavement will be milled off and crews will start stabilizing the subgrade with bulk lime. We anticipate Glendora Ct. being completed within the next 3-4 weeks.
During the milling process on Val Verde Ct, crews encountered unanticipated subgrade issues that required the project to be converted from a mill and overlay to a reconstruction. This scope change has resulted in additional time being required on Val Verde Ct than originally anticipated. We anticipate the reconstruction of Val Verde being complete by the end of July.
City crews have ordered soil samples from the rest of the segments throughout the subdivision to better anticipate subgrade issues and speed up work on any roads that may require reconstruction. In terms of next steps, the construction crew will be moving to the west end of Palo Verde Dr. and Brisas Ct. to perform reconstruction of those segments. The mill and overlay crew will be going to the west side of Buena Vista Dr. to perform a mill and overlay of this segment.
Due to the upcoming start of the school year, we plan to delay the reconstruction of Montecito Dr until next summer. During the school year, work will continue in the remainder of the neighborhood; however, city crews will not perform construction or operate equipment during school opening or release to avoid conflicts with students or parents traveling to or from school.
Construction has concluded.