Riney Road East Improvement Project

Share Riney Road East Improvement Project on Facebook Share Riney Road East Improvement Project on Twitter Share Riney Road East Improvement Project on Linkedin Email Riney Road East Improvement Project link


The purpose of this project is to widen Riney Rd to its full roadway width in coordination with the opening of a new DISD elementary school. The Riney Road East Improvement Project will include two segments of concrete roadway. The first segment to be widen consists of approximately 1310 linear feet of street along the frontage of the G. Roland Vela Soccer Complex. The second segment to be widen consists of 270 linear feet along the frontage of two single family residential lots located on Riney Road.


The project will also consist of a 10-foot-wide concrete hike and bike trail. Once constructed, the hike and bike trail will tie the new DISD elementary school property to the City of Denton Northlakes Park trails system. The hike and bike trail will require a prefabricated pedestrian bridge to cross an existing drainage swale and will connect to a concrete sidewalk East of the softball fields.


The purpose of this project is to widen Riney Rd to its full roadway width in coordination with the opening of a new DISD elementary school. The Riney Road East Improvement Project will include two segments of concrete roadway. The first segment to be widen consists of approximately 1310 linear feet of street along the frontage of the G. Roland Vela Soccer Complex. The second segment to be widen consists of 270 linear feet along the frontage of two single family residential lots located on Riney Road.


The project will also consist of a 10-foot-wide concrete hike and bike trail. Once constructed, the hike and bike trail will tie the new DISD elementary school property to the City of Denton Northlakes Park trails system. The hike and bike trail will require a prefabricated pedestrian bridge to cross an existing drainage swale and will connect to a concrete sidewalk East of the softball fields.

  • Consultant Engineer continues to work on Plan Set!

    Share Consultant Engineer continues to work on Plan Set! on Facebook Share Consultant Engineer continues to work on Plan Set! on Twitter Share Consultant Engineer continues to work on Plan Set! on Linkedin Email Consultant Engineer continues to work on Plan Set! link

    Consultant Engineer continues to work on the plan set to be able to submit to the City the 90% plan set in August 2024.

  • Right of Way Acquistion Process has started!

    Share Right of Way Acquistion Process has started! on Facebook Share Right of Way Acquistion Process has started! on Twitter Share Right of Way Acquistion Process has started! on Linkedin Email Right of Way Acquistion Process has started! link

    The Consultant Engineer has prepared the Surveyor's Exhibits needed to begin the right-of-way acquisition process.

  • The 60% Plan Set is being reviewed by both internal and external stakeholders!

    Share The 60% Plan Set is being reviewed by both internal and external stakeholders! on Facebook Share The 60% Plan Set is being reviewed by both internal and external stakeholders! on Twitter Share The 60% Plan Set is being reviewed by both internal and external stakeholders! on Linkedin Email The 60% Plan Set is being reviewed by both internal and external stakeholders! link

    The 60% plan set continues to be reviewed by City Staff.

  • 60% Plan Set submitted to the City.

    Share 60% Plan Set submitted to the City. on Facebook Share 60% Plan Set submitted to the City. on Twitter Share 60% Plan Set submitted to the City. on Linkedin Email 60% Plan Set submitted to the City. link

    Binkley & Barfield has submitted their prepared 60% Plan Set for the City to review.

  • Binkley & Barfield is working on the project schematic plans.

    Share Binkley & Barfield is working on the project schematic plans. on Facebook Share Binkley & Barfield is working on the project schematic plans. on Twitter Share Binkley & Barfield is working on the project schematic plans. on Linkedin Email Binkley & Barfield is working on the project schematic plans. link

    The Consultant Engineer is busy working on the project schematic plans getting them ready for their submittal in March 2024.

  • Design Contract Awarded

    Share Design Contract Awarded on Facebook Share Design Contract Awarded on Twitter Share Design Contract Awarded on Linkedin Email Design Contract Awarded link

    On November 14, 2023, the design contract was awarded to Binkley & Barfield, Inc. Binkley & Barfield will be working both with internal and external stakeholders to move forward with the design.

Page last updated: 03 Nov 2025, 09:31 AM