Denton Solid Waste Fleet
The Denton Solid Waste Fleet Shop project will comprise 14,500 sf of single-story concrete tilt wall construction. The project will include six (6) service bays to accommodate large Solid Waste vehicles and equipment, and office space for personnel. The new facility will include parking and holding spaces for equipment under repair that will accommodate the large vehicle size necessary for Solid Waste operations.
The Denton Solid Waste Fleet Shop project will comprise 14,500 sf of single-story concrete tilt wall construction. The project will include six (6) service bays to accommodate large Solid Waste vehicles and equipment, and office space for personnel. The new facility will include parking and holding spaces for equipment under repair that will accommodate the large vehicle size necessary for Solid Waste operations.
-
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
ACHIEVEMENTS:
üRoofing dried inüPavement in progressüTransformer installedüOverhead door installationNEXT STEPS:
qMEP startupqElectrical room buildoutqFinishes -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
ACHIEVEMENTS:
Roofing dried in
Structural slab complete
Commissioning kickoff complete
Pavement in progress
NEXT STEPS:
Transformer installation
Pavement completion
Overhead door installation
-
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress linkACHIEVEMENTS:
üTilt wall panels completely erectedüSteel erection completeüRoofing dried inüStructural slab in progressüHVAC units onsiteNEXT STEPS:
qSite grading and pavementqInternal MEP systems -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
ACHIEVEMENTS:
üTilt wall panels completely erectedüSteel erection completeüRoofing in progressNEXT STEPS:
qRoof completionqStructural slab completion -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress linkACHIEVEMENTS:
üTilt wall panels completely erectedüSteel erection in progressNEXT STEPS:
qStructural steel completionqStructural slab completionqExterior finishing -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress linkACHIEVEMENTS:
üTilt wall planning meetingüGrade beams completeüCasting beds completeüTilt wall panels formedNEXT STEPS:
qTilt wall erectionqStructural steelqBuilding slab -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
ACHIEVEMENTS:
üContractor MobilizationüGeotechnical Testing Contract ExecutedüTilt wall planning meetingüGrade beams completeüCasting beds completeNEXT STEPS:
qUtilitiesqTilt wall panels pouredqVertical construction -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress linkACHIEVEMENTS:
üContractor MobilizationüGeotechnical Testing Contract ExecutedüTilt wall planning meetingüFirst grade beam pourNEXT STEPS:
qLong Lead Item ProcurementqUtilitiesqGrade beam completion -
Construction Progress
Share Construction Progress on Facebook Share Construction Progress on Twitter Share Construction Progress on Linkedin Email Construction Progress link
ACHIEVEMENTS:
üBuilding Permit CompleteüUtility Permit CompleteüContractor MobilizationüPier Drilling in ProgressüGeotechnical Testing Contract ExecutedNEXT STEPS:
qLong Lead Item ProcurementqUtilitiesqGrade beamsThank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends
No thanks -
Construction Phase
Share Construction Phase on Facebook Share Construction Phase on Twitter Share Construction Phase on Linkedin Email Construction Phase linkACHIEVEMENTS:
üBuilding Permit CompleteüUtility Permit CompleteüContractor MobilizationüDemo CompleteNEXT STEPS:
qGeotechnical PUBqLong Lead Item ProcurementqBuilding Pad prep
Who's Listening
-
Phone (940) 349-7107 Email giovanni.pineiro-villalba@cityofdenton.com -
Phone (940) 349-8182 Email aaron.skinner@cityofdenton.com

