2020 Street Bundle II - Southwest Sector
Consultation has concluded
The 2020 Street Reconstruction Bundle: Southwest Sector Project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. The Southwest Sector phase includes the street reconstruction of N. Texas Boulevard, Chestnut Street from Welch Street to Bernard Street; and Welch Street from Collins Street to Fannin Street (view map below). The street reconstruction will include new curb and gutter, asphalt roadways as well as upgraded water and wastewater facilities.
Project Status
Project Timeline August 2021- January, 2023*
*Estimated project phase timelines are for listed for active orContinue reading
The 2020 Street Reconstruction Bundle: Southwest Sector Project is a part of a multi-phase street reconstruction project to rebuild existing streets that have reached the end of their useful life. The Southwest Sector phase includes the street reconstruction of N. Texas Boulevard, Chestnut Street from Welch Street to Bernard Street; and Welch Street from Collins Street to Fannin Street (view map below). The street reconstruction will include new curb and gutter, asphalt roadways as well as upgraded water and wastewater facilities.
Project Status
Project Timeline August 2021- January, 2023*
*Estimated project phase timelines are for listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction.
Estimate project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.
-
Project Completion and Closeout
Share on Facebook Share on Twitter Share on Linkedin Email this linkConstruction for the 2020 Street Bundle Sector II project has been completed.
Project closeout has started with completion expected Q1 2023
-
Project Update
Share on Facebook Share on Twitter Share on Linkedin Email this linkPaving operations on Stella and North Texas Ave. have been completed.
Project construction is in the final stages of restoration with a completion anticipated in January 2023.
-
North Texas Blvd. and Stella Ave. Paving
Share on Facebook Share on Twitter Share on Linkedin Email this linkPaving operations on Stella Ave.nearing completion.
Street restoration and paving on North Texas Blvd. are nearing completion with the last phases between Stella and West Oak being completed.
Expect changing traffic patterns during construction.
-
North Texas Blvd. and Stella Ave. Paving
Share on Facebook Share on Twitter Share on Linkedin Email this linkPaving operations on Stella Ave. are nearing completion.
Street restoration and paving phases on North Texas Blvd. continue between West Highland St. and West Oak St.
Expect changing traffic patterns during construction.
-
North Texas Blvd. and Stella Ave Paving
Share on Facebook Share on Twitter Share on Linkedin Email this linkStreet restoration and paving are underway on North Texas Blvd. and Stella Ave.
Paving will be performed in several different phases to allow continued traffic flow in the area.
Expect changing traffic patterns during construction.
-
North Texas Blvd. Utility Relocations
Share on Facebook Share on Twitter Share on Linkedin Email this linkUtility relocations are currently underway on North Texas Blvd.
Construction will be performed in phases.
Expect changing traffic patterns during construction.
-
Stella Ave. Utility Relocations Begin Week of 10/25/21
Share on Facebook Share on Twitter Share on Linkedin Email this linkUtility relocations are scheduled to begin on Stella Ave. the week of 10/25/21.
Street parking will not be allowed in the construction zone and we request that traffic control is followed at all times.
-
Construction Has Started
Share on Facebook Share on Twitter Share on Linkedin Email this linkConstruction on both the Welch and Chestnut segments is ongoing.
Street parking will not be allowed in the construction zone and we request that traffic control is followed at all times.
-
Construction Contractor Selected
Share on Facebook Share on Twitter Share on Linkedin Email this linkTuesday, June 8, the contract for the 2020 Street Reconstruction Bundle: Southwest Sector project was approved for award to Jagoe-Public Company by the Denton City Council. A construction schedule and expected impacts will be updated on the project page and provided to residents in the area prior to construction.
-
View the April 15, 2021 Meeting Replay
Share on Facebook Share on Twitter Share on Linkedin Email this linkOn Thursday, April 15, City staff hosted a virtual community meeting regarding the 2020 Street Reconstruction Bundle: Southwest Sector project. View the meeting replay below.
Stay Updated and Have Your Say
Click HERE to register to stay informed and ask the project manager a question about the 2020 Street Reconstruction Bundle: Southwest Sector Capital Improvement Project.
Project Information
Estimated Cost: $5 Million
Sponsoring Department: Capital Projects/Engineering
Funding Source: 2012/2014 Bond Program
Project Location: Various Street Locations
Contact Information:
Multi-phase projects may require different project managers. Below are the current project managers and the phase they manage.
Who's Listening
-
Construction Projects Manager
Phone (940) 349-8909 Email scott.fettig@cityofdenton.com -
Capital Projects Program Manager