PHASE 3 - FM1515/Airport Road to Roselawn

Phase 3 is progressing with installation of the new water and sanitary sewer systems as well as new underground drainage infrastructure at both the north and south ends of the project. On January 27th, Bonnie Brae at Airport Road was fully closed to all traffic. The contractor is working to complete all the underground improvements as well as paving of the section of Bonnie Brae between Airport Road and Main Stadium Drive to ensure this section of roadway can be open and accept traffic from TxDOT's 35E-Merge project which is now also under construction. Weather permitting, paving activities in this section will be complete and re-open to traffic in mid June 2025.
Paving has begun on the south end of the project near Roselawn. Sections of both the north and south bound lanes have been installed between Erskine and Roselawn.
Ongoing spot road closures through-out south Bonnie Brae will continue as underground storm drain facilities are installed and utility services are crossed under Bonnie Brae and tied-in to the new infrastructure. Message boards will be updated in advance of these planned closures. Follow posted detour signs.
The overall project is expected to be complete in November of 2026. Look for progress pictures and videos under the coordinating tab on the right.
We appreciate everyone's patience as we work hard to make these necessary improvements. Please remember to be considerate of work zones and road conditions, driving safely and according to the conditions.