Bonnie Brae Street

Share on Facebook Share on Twitter Share on Linkedin Email this link

To accommodate mobility needs, Bonnie Brae Street is being expanded from a two-lane undivided road to a four-lane divided road. This six phase project has one phase completed, and two phases actively in construction that are scheduled for completion by 2021. Below are the project limits and status for each phase.

Project Status

Phase 1 (Roselawn to North of Vintage Boulevard)
Phase 2 (I-35W TO US 377) | Project Timeline: 2020 - 2021*

Phase 3 (Roselawn to IH-35E) | Project Timeline: 2022 - 2024*

Phase 4B (I-35E to Scripture) | Project Timeline: TBD

Phase 5 (Scripture Roundabout to US380) |

To accommodate mobility needs, Bonnie Brae Street is being expanded from a two-lane undivided road to a four-lane divided road. This six phase project has one phase completed, and two phases actively in construction that are scheduled for completion by 2021. Below are the project limits and status for each phase.

Project Status

Phase 1 (Roselawn to North of Vintage Boulevard)
Phase 2 (I-35W TO US 377) | Project Timeline: 2020 - 2021*

Phase 3 (Roselawn to IH-35E) | Project Timeline: 2022 - 2024*

Phase 4B (I-35E to Scripture) | Project Timeline: TBD

Phase 5 (Scripture Roundabout to US380) | Project Timeline: TBD

Phase 6 (US380 to US77) | Project Timeline: 2022 - 2023*

Phase 4A (Bonnie Brae at Scripture Roundabout) | Project Timeline: 2019 - 2020*

*Estimated project phase timelines are for listed for active or planned projects. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction.
Estimate project timelines may change due to weather, contractor scheduling, among other factors and will be updated as needed.

  • Bonnie Brae Phase 2 Update: Traffic Pattern Shift on Bonnie Brae Street Beginning Next Week

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Beginning Monday, August 9, Bonnie Brae Street from Vintage Boulevard to Old Bonnie Brae, southbound traffic will be shifted to the newly constructed lane to allow crews to continue paving at the intersection. Motorists traveling in the area will be on this new traffic alignment until the Bonnie Brae Phase 2 (Bonnie Brae from I-35W to US 377) construction activities are expected to be complete in September 2021. Delays and backups are possible so motorists are reminded to use caution when traveling in the area and adhere to all posted construction signage.

  • New Lanes Now Open on Bonnie Brae Street

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    New lanes of traffic on Bonnie Brae Street are now open. Today, April 14, construction crews opened the newly constructed westbound traffic lanes on Vintage Blvd from Bonnie Brae Street to I-35W and shifted traffic from the old lanes so they can begin reconstruction. Motorists traveling in the area will be on this new traffic alignment until this phase of Bonnie Brae project is expected to complete in early June 2021.

    Current Construction and Traffic Impacts
    Construction to reconstruct Bonnie Brae Street from Vintage Boulevard to Napa Valley is now underway, as well as work to connect the new Bonnie Brae bridge for traffic traveling southbound on Bonnie Brae Street from the newly constructed bridges to Vintage Blvd.

    Motorists are reminded to use caution when traveling in the area. Arrow boards to alert drivers of the current construction and new traffic pattern are in place.

  • Project Phases Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Phase 2 (Vintage and the intersection of Vintage at Bonnie Brae Street) is scheduled for completion in Q3 2021. Phase 3 (Roselawn to I-35) is expected to start construction in summer 2021 and has an estimated completion date of Q3 2023. Phase 4B-6 (I-35 to US77) are currently in the design phase and will progress to advertise, bid and award phase when complete.

  • Vintage Boulevard to Roselawn Drive Southbound Lanes Now Open to Traffic

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Beginning today, Feb. 8, the southbound lanes on the new bridge at Bonnie Brae Street from Vintage Boulevard to Roselawn Drive is now open to traffic as part of the Bonnie Brae Phase 1 project! The Bonnie Brae Phase 1 project limits include Bonnie Brae Street from Roselawn Drive to north of Vintage Boulevard.

    With traffic in both directions now open on the new bridge, crews will begin reconstructing old Bonnie Brae Street. To allow crews to safely complete the remaining construction activities, intermittent lane closures may be in place as crews safely complete the remaining construction activities. The Bonnie Brae Phase 1 project remains on schedule for construction activities to be complete by March 2021.

  • Phase 1 Construction Video Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The Construction Projects Manager provides a construction update on Phase 1 of the Bonnie Brae Street project.

  • New Bridge Scheduled to Open to Traffic

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Weather permitting, Tuesday, Jan. 19, crews will begin switching the northbound traffic lanes of Bonnie Brae St. from Vintage Blvd. to Roselawn Dr. onto the new bridge as part of Phase 1.

    The traffic switch is expected to be complete by 5 p.m. The southbound traffic lanes are scheduled to remain on the existing roadway for another 4 to 5 weeks, weather permitting, until the intersection construction is complete. Until the switch is complete, and over the new few weeks, intermittent lane closures may be in place as crews safely complete the remaining construction activities. Phase 1 remains on schedule to be open by March 2021.

  • Phase 1 Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Construction for Phase 1 (Roselawn to north of Vintage) is substantially complete. Traffic is scheduled to be placed on the bridge in the coming weeks. Final construction activities and clean-up are in progress for Phase 1. Construction activities for Phase 2 (Vintage Boulevard; I35W to US377) currently include roadway paving, street light conduit installation and inlet top installation.

  • Replay the Phase 3 Dec. 3, 2020 Virtual Community Meeting

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image


  • Attend the Phase 6 Virtual Community Meeting Thursday, Dec. 10

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The City of Denton will hold a virtual Community Meeting on Thursday, Dec. 10, regarding the Bonnie Brae Phase 6 project located at Bonnie Brae Street from University Drive/US-380 to US-77.

    The City will host the virtual community meeting to provide residents and property owners the opportunity to:

    • Receive an update on the status of the Bonnie Brae Phase 6 project; and
    • Discuss input and concerns from community members.

    Staff from the City of Denton Capital Projects/Engineering and Real Estate departments will be available to discuss the project and answer questions from those participating in the virtual meeting. The meeting will be hosted online using a remote format through the video-conferencing interface Zoom. Instructions on how to attend and participate in the virtual meeting are listed HERE.

    For more details on virtual community meetings, visit www.cityofdenton.com/virtualcommunitymeeting.

  • Attend the Phase 3 Virtual Community Meeting Thursday, Dec. 3

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    The City of Denton will hold a virtual Community Meeting on Thursday, Dec. 3, regarding the Bonnie Brae Phase 3 project located at Bonnie Brae Street from Roselawn Drive to IH-35E.

    The City will host the virtual community meeting to provide residents and property owners the opportunity to:

    • Receive an update on the status of the Bonnie Brae Phase 3 project; and
    • Discuss input and concerns from community members.

    Staff from the City of Denton will be available to discuss the project and answer questions from those participating in the virtual meeting. The meeting will be hosted online using a remote format through the video-conferencing interface Zoom. Instructions on how to attend and participate in the virtual meeting are listed HERE.

    For more details on virtual community meetings, visit www.cityofdenton.com/virtualcommunitymeeting.