Bonnie Brae Street

Share Bonnie Brae Street on Facebook Share Bonnie Brae Street on Twitter Share Bonnie Brae Street on Linkedin Email Bonnie Brae Street link

To accommodate mobility needs, Bonnie Brae Street is being expanded from a two-lane undivided rural roadway to a four-lane divided urban street. This six-phase project has three phases completed (1,2 & 4A), Phase 3 is currently in construction. Below are the project limits and status for each phase.

PROJECT PHASES & STATUS

Phase 1 (Roselawn to North of Vintage Boulevard) - COMPLETE

Phase 2 (I-35W TO US 377 Includes Vintage Blvd) - COMPLETE

Phase 3 (Roselawn to IH-35E) | Project Timeline: 2023 - 2026

Sundt Construction was issued a Notice to Proceed on October 16, 2023. The project has a

To accommodate mobility needs, Bonnie Brae Street is being expanded from a two-lane undivided rural roadway to a four-lane divided urban street. This six-phase project has three phases completed (1,2 & 4A), Phase 3 is currently in construction. Below are the project limits and status for each phase.

PROJECT PHASES & STATUS

Phase 1 (Roselawn to North of Vintage Boulevard) - COMPLETE

Phase 2 (I-35W TO US 377 Includes Vintage Blvd) - COMPLETE

Phase 3 (Roselawn to IH-35E) | Project Timeline: 2023 - 2026

Sundt Construction was issued a Notice to Proceed on October 16, 2023. The project has a 30 month construction schedule.

Any full or partial lane closures lasting longer than 2 days will be updated on the city street closure report: Weekly Street Closure Report. Message Boards will be updated with any closures and detours will be posted accordingly.

A virtual community meeting was held on Wednesday September 20, 2023, at 6pm. You can view the presentation in the Community Updates tool on your right.


Phase 4A (Roundabout at Scripture | Project Timeline: 2019 - 2020 - COMPLETE

Phase 4B (I-35E Service Road to Roundabout at Scripture) | Project Timeline: TBD
Phase 5 (Roundabout at Scripture to US380) | Project Timeline: TBD

Recently, this section of roadway was re-paved as part of the North South Water Phase 3, 42-inch Water Transmission Main project. Phases 4B & 5 of the Bonnie Brae Roadway Project will provide a 4-lane divided roadway with a raised median and tie into the US380-University Drive Intersection matching the Bonnie Brae Phase 6 alignment.

Phase 6 (US380 to US77) | Project Construction Timeline: 2024 - 2026


Project phases are listed for active and/or planned projects.  These phases reflect the range of a project life cycle from project initiation to project completion & close-out.  The year range reflected is for the estimated construction timeline only.   These estimated construction timelines may change due to weather, contractor scheduling, material delays, and/or other factors. Timelines will be updated when needed.  All Bonnie Brae Phases are shown, including COMPLETED Phases in an effort to show the entire Bonnie Brae Corridor. 

Ask the Project Manager

Submit your questions on the Bonnie Brae project to the Construction Projects Manager here. We will respond to your question within three (3) business days. 

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share What is the Status of BB from vintage to 377? Will it be closed for sometime? on Facebook Share What is the Status of BB from vintage to 377? Will it be closed for sometime? on Twitter Share What is the Status of BB from vintage to 377? Will it be closed for sometime? on Linkedin Email What is the Status of BB from vintage to 377? Will it be closed for sometime? link

    What is the Status of BB from vintage to 377? Will it be closed for sometime?

    Eswaybar asked 9 months ago

    Good morning, The section of Bonnie Brae near Vintage in question is actually a Water Utilities project and not part of the roadway Improvements.  The Weekly Street Closure Report shows the project to be closed from August 7 to August 18.

    The contact for the project is Jamie Bond.  You can reach him directly at jamie.bond@cityofdenton.com

    Thank you,

    Robin Davis, PMP
    Capital Projects

  • Share When is the expected completion of the construction on Bonnie brae? on Facebook Share When is the expected completion of the construction on Bonnie brae? on Twitter Share When is the expected completion of the construction on Bonnie brae? on Linkedin Email When is the expected completion of the construction on Bonnie brae? link

    When is the expected completion of the construction on Bonnie brae?

    Charlottemcd20 asked almost 2 years ago

    Hello and thank you for reaching out to us over Discuss Denton. Because Bonnie Brae is such a large project, it has been broken up into multiple phases, each with their own construction timeline. 

    North South Water Phase 3 has completed the installation of the 42-inch Water Transmission Main from I-35E service road to near Panhandle and are now working on roadway mill and overlay. Weather permitting, paving is expected to be complete by the end of May.

    Bonnie Brae Phase 6 from US 380/University to US 77/Elm Street is tentatively scheduled to begin in October of this year and complete in December of 2024.

    Bonnie Brae phase 3 from FM 1515 to Roselawn, tying into the new alignment (Bonnie Brae Phase 1) is expected to begin construction this winter and anticipated to be complete within 18 months.

    These schedules are tentative as we may experience timeline impacts due to  weather, material availability, and other unforeseen circumstances.

    Please feel free to reach out to our program manager Kyle.Pedigo@cityofdenton.com with any additional questions related to the project.

  • Share Hi, I’m a resident living close to North Lake Park. I’m also a Denton ISD employee. I’m wondering what is your time line for construction for Bonnie Brae north past the new High School?? on Facebook Share Hi, I’m a resident living close to North Lake Park. I’m also a Denton ISD employee. I’m wondering what is your time line for construction for Bonnie Brae north past the new High School?? on Twitter Share Hi, I’m a resident living close to North Lake Park. I’m also a Denton ISD employee. I’m wondering what is your time line for construction for Bonnie Brae north past the new High School?? on Linkedin Email Hi, I’m a resident living close to North Lake Park. I’m also a Denton ISD employee. I’m wondering what is your time line for construction for Bonnie Brae north past the new High School?? link

    Hi, I’m a resident living close to North Lake Park. I’m also a Denton ISD employee. I’m wondering what is your time line for construction for Bonnie Brae north past the new High School??

    Larry asked over 2 years ago

    Hello and thank you for your question! We are currently on track to begin this project starting in Q4 of 2022 and complete in Q3 of 2024. If you would like more information, feel free to reach out to the Project Manager Eric Cooper at Eric.Cooper@cityofdenton.com. Thank you.

  • Share Why is the construction project along Vintage Blvd. from Hwy 377 to IH35W taking so long? It has been about 2 years now and they still do not seem anywhere near completion. Every 6 months it seems they are redoing another project along either side of the divided road. Do they keep messig up and have to redo it or what? What is the expected timeframe for completion? According to the website, it appears that it was supposed to be finished in 2021. It is now 2022. on Facebook Share Why is the construction project along Vintage Blvd. from Hwy 377 to IH35W taking so long? It has been about 2 years now and they still do not seem anywhere near completion. Every 6 months it seems they are redoing another project along either side of the divided road. Do they keep messig up and have to redo it or what? What is the expected timeframe for completion? According to the website, it appears that it was supposed to be finished in 2021. It is now 2022. on Twitter Share Why is the construction project along Vintage Blvd. from Hwy 377 to IH35W taking so long? It has been about 2 years now and they still do not seem anywhere near completion. Every 6 months it seems they are redoing another project along either side of the divided road. Do they keep messig up and have to redo it or what? What is the expected timeframe for completion? According to the website, it appears that it was supposed to be finished in 2021. It is now 2022. on Linkedin Email Why is the construction project along Vintage Blvd. from Hwy 377 to IH35W taking so long? It has been about 2 years now and they still do not seem anywhere near completion. Every 6 months it seems they are redoing another project along either side of the divided road. Do they keep messig up and have to redo it or what? What is the expected timeframe for completion? According to the website, it appears that it was supposed to be finished in 2021. It is now 2022. link

    Why is the construction project along Vintage Blvd. from Hwy 377 to IH35W taking so long? It has been about 2 years now and they still do not seem anywhere near completion. Every 6 months it seems they are redoing another project along either side of the divided road. Do they keep messig up and have to redo it or what? What is the expected timeframe for completion? According to the website, it appears that it was supposed to be finished in 2021. It is now 2022.

    Deano asked over 2 years ago

    Thank you for submitting this questions. The Vintage portion of Bonnie Brae is set to be complete by the end of Q1 2022. The project has seen significant material delays due to the COVID-19 pandemic. The City has also added several panel replacements that were needed along the existing lanes of Vintage. Once the final paving is complete, striping will take place and the majority of the traffic control devices will be removed. Engineering staff is also working with Parks and Recreation staff to install irrigation in the medians for trees. If you would like more information feel free to reach out to the Project Manager Seth Garcia at Seth.Garcia@cityofdenton.com. Thank you.

Page last updated: 11 Apr 2024, 01:11 PM