To accommodate mobility needs, Bonnie Brae Street is being expanded from a two-lane undivided rural roadway to a four-lane divided urban street. This six-phase project has three phases completed (1,2 & 4A), Phase 3 is currently in construction. Below are the project limits and status for each phase.

PROJECT PHASES & STATUS

Phase 1 (Roselawn to North of Vintage Boulevard) - COMPLETE

Phase 2 (I-35W TO US 377 Includes Vintage Blvd) - COMPLETE

Phase 3 (Roselawn to IH-35E) IN CONSTRUCTION | Project Timeline: 2023 - 2026

Sundt Construction was issued a Notice to Proceed on October 16, 2023. The project

To accommodate mobility needs, Bonnie Brae Street is being expanded from a two-lane undivided rural roadway to a four-lane divided urban street. This six-phase project has three phases completed (1,2 & 4A), Phase 3 is currently in construction. Below are the project limits and status for each phase.

PROJECT PHASES & STATUS

Phase 1 (Roselawn to North of Vintage Boulevard) - COMPLETE

Phase 2 (I-35W TO US 377 Includes Vintage Blvd) - COMPLETE

Phase 3 (Roselawn to IH-35E) IN CONSTRUCTION | Project Timeline: 2023 - 2026

Sundt Construction was issued a Notice to Proceed on October 16, 2023. The project is expected to be complete in November 2026 (weather permitting).

Any full or partial lane closures lasting longer than 2 days will be updated on the city street closure report: Weekly Street Closure Report. Message Boards will be updated with any closures and detours will be posted accordingly.

A virtual community meeting was held on Wednesday September 20, 2023, at 6pm. You can view the presentation in the Community Updates tool on your right. Look for any specific updates below...


Phase 4A (Roundabout at Scripture | Project Timeline: 2019 - 2020 - COMPLETE

Phase 4B (I-35E Service Road to Roundabout at Scripture) | Project Timeline: TBD
Phase 5 (Roundabout at Scripture to US380) | Project Timeline: TBD

Recently, this section of roadway was re-paved as part of the North South Water Phase 3, 42-inch Water Transmission Main project. Phases 4B & 5 of the Bonnie Brae Roadway Project will provide a 4-lane divided roadway with a raised median and tie into the US380-University Drive Intersection matching the Bonnie Brae Phase 6 alignment.

Phase 6 (US380 to US77) IN CONSTRUCTION | Project Construction Timeline: 2025 - 2027


Project phases are listed for active and/or planned projects.  These phases reflect the range of a project life cycle from project initiation to project completion & close-out.  The year range reflected is for the estimated construction timeline only.   These estimated construction timelines may change due to weather, contractor scheduling, material delays, and/or other factors. Timelines will be updated when needed.  All Bonnie Brae Phases are shown, including COMPLETED Phases in an effort to show the entire Bonnie Brae Corridor. 

Ask the Project Manager

Submit your questions on the Bonnie Brae project to the Construction Projects Manager here. We will respond to your question within three (3) business days. 

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Good Morning, The traffic from airport road to the 3 way stop on Bonnie Brae has become atrocious because of the newly added off-ramp from 35W N that tees right in before the stop sign. Is this the final solution for airport road/bonnie brae? When is the bridge going to be expanded to add more lanes? And do you have a timeline for this? Technically, everyone on airport road is supposed to yield to the off-ramp, which does not happen. It takes approximately 25-30 minutes to get from airport road to the frontage road any time between 3 and 6 pm. Are there updated plans somewhere that we can access to understand the city's plan? Thank you, Frustrated Denton Man on Facebook Share Good Morning, The traffic from airport road to the 3 way stop on Bonnie Brae has become atrocious because of the newly added off-ramp from 35W N that tees right in before the stop sign. Is this the final solution for airport road/bonnie brae? When is the bridge going to be expanded to add more lanes? And do you have a timeline for this? Technically, everyone on airport road is supposed to yield to the off-ramp, which does not happen. It takes approximately 25-30 minutes to get from airport road to the frontage road any time between 3 and 6 pm. Are there updated plans somewhere that we can access to understand the city's plan? Thank you, Frustrated Denton Man on Twitter Share Good Morning, The traffic from airport road to the 3 way stop on Bonnie Brae has become atrocious because of the newly added off-ramp from 35W N that tees right in before the stop sign. Is this the final solution for airport road/bonnie brae? When is the bridge going to be expanded to add more lanes? And do you have a timeline for this? Technically, everyone on airport road is supposed to yield to the off-ramp, which does not happen. It takes approximately 25-30 minutes to get from airport road to the frontage road any time between 3 and 6 pm. Are there updated plans somewhere that we can access to understand the city's plan? Thank you, Frustrated Denton Man on Linkedin Email Good Morning, The traffic from airport road to the 3 way stop on Bonnie Brae has become atrocious because of the newly added off-ramp from 35W N that tees right in before the stop sign. Is this the final solution for airport road/bonnie brae? When is the bridge going to be expanded to add more lanes? And do you have a timeline for this? Technically, everyone on airport road is supposed to yield to the off-ramp, which does not happen. It takes approximately 25-30 minutes to get from airport road to the frontage road any time between 3 and 6 pm. Are there updated plans somewhere that we can access to understand the city's plan? Thank you, Frustrated Denton Man link

    Good Morning, The traffic from airport road to the 3 way stop on Bonnie Brae has become atrocious because of the newly added off-ramp from 35W N that tees right in before the stop sign. Is this the final solution for airport road/bonnie brae? When is the bridge going to be expanded to add more lanes? And do you have a timeline for this? Technically, everyone on airport road is supposed to yield to the off-ramp, which does not happen. It takes approximately 25-30 minutes to get from airport road to the frontage road any time between 3 and 6 pm. Are there updated plans somewhere that we can access to understand the city's plan? Thank you, Frustrated Denton Man

    Frustrated Denton Man asked 11 days ago

    Good Morning Frustrated Denton Man,

    Airport Road/FM 1515 is managed by TxDOT.  TxDOT does have plans for the FM 1515 expansion which also includes the bridge. The online project tracker on TxDOT's website (https://apps3.txdot.gov/apps-cq/project_tracker/) shows construction is still out by several years with an estimated letting date of September 2031, which is most likely to have construction beginning in January 2032. TxDOT shows to open the ramp for westbound Airport Road on December 20th which will hopefully help some of this issue. The current schedule for the traffic signal at Bonnie Brae and Airport Road to be completely installed and activated is March 2026. We are working with our contractor to see if this schedule can be expedited.  In the meantime, I have added some alternative route options as a news feed for BB3 update.    I will be working with TxDOT to see if there are other things we can do to help alleviate the stacking issue during peak times.

    Robin Davis, PMP
    Project Manager, Capital Projects

  • Share Why is the traffic light at Bonnie Brae and Airport Road not operational? And when will it be operational? This is significantly impacting the lives of those working down Airport Road in a negative way. on Facebook Share Why is the traffic light at Bonnie Brae and Airport Road not operational? And when will it be operational? This is significantly impacting the lives of those working down Airport Road in a negative way. on Twitter Share Why is the traffic light at Bonnie Brae and Airport Road not operational? And when will it be operational? This is significantly impacting the lives of those working down Airport Road in a negative way. on Linkedin Email Why is the traffic light at Bonnie Brae and Airport Road not operational? And when will it be operational? This is significantly impacting the lives of those working down Airport Road in a negative way. link

    Why is the traffic light at Bonnie Brae and Airport Road not operational? And when will it be operational? This is significantly impacting the lives of those working down Airport Road in a negative way.

    Traffic Nightmare asked 11 days ago

    Good Morning Traffic Nightmare,

    The new traffic signal is being installed as part of the Bonnie Brae Phase 3 Project and still needs a few steps completed before it can be activated. There is one more signal pole/arm left to install on the southwest corner of the intersection.  The foundation for it is actually being poured today.  Electric service to the signals also needs to be installed and is expected to be complete by the end of January/early February.  Upon activation,  the signals are required to flash for two (2) weeks prior to full operation. Weather permitting, we should have a fully operational traffic signal at Bonnie Brae and Airport Road by March 2026.

    Kind Regards,

    Robin Davis, PMP
    Project Manager - Bonnie Brae Phase 3
    Capital Projects


  • Share Will Uptown Apartments off of Oak be affected by the protect? Like will it eventually have to shut down? on Facebook Share Will Uptown Apartments off of Oak be affected by the protect? Like will it eventually have to shut down? on Twitter Share Will Uptown Apartments off of Oak be affected by the protect? Like will it eventually have to shut down? on Linkedin Email Will Uptown Apartments off of Oak be affected by the protect? Like will it eventually have to shut down? link

    Will Uptown Apartments off of Oak be affected by the protect? Like will it eventually have to shut down?

    Motts asked 9 months ago

    Hello,

    Thank you for reaching out.  It sounds like you are concerned with the entrances off of the service road to the Apartment Complex - that would be a question for TxDOT as they are over the I-35 expansion project including the service roads.  They can be reached at 940.387.1414. Neither of the Bonnie Brae projects currently under construction (phases 3 and 6) are affecting Uptown Apartments off Oak Street.  

  • Share I asked about getting potholes filled south of the soccer field on Bonnybrae that was 27 days ago. They have not been filled as you said they are please fill them a lot of people use that road thank you. on Facebook Share I asked about getting potholes filled south of the soccer field on Bonnybrae that was 27 days ago. They have not been filled as you said they are please fill them a lot of people use that road thank you. on Twitter Share I asked about getting potholes filled south of the soccer field on Bonnybrae that was 27 days ago. They have not been filled as you said they are please fill them a lot of people use that road thank you. on Linkedin Email I asked about getting potholes filled south of the soccer field on Bonnybrae that was 27 days ago. They have not been filled as you said they are please fill them a lot of people use that road thank you. link

    I asked about getting potholes filled south of the soccer field on Bonnybrae that was 27 days ago. They have not been filled as you said they are please fill them a lot of people use that road thank you.

    connie Kerr asked about 1 year ago

    The contactor will continue performing pothole maintenance activities. We ask for the public's patience and understanding as this is a very active construction site.  Please drive safe and according the conditions of the roadway.

  • Share when is phase 3 gonna be done? and are they about to pave it? on Facebook Share when is phase 3 gonna be done? and are they about to pave it? on Twitter Share when is phase 3 gonna be done? and are they about to pave it? on Linkedin Email when is phase 3 gonna be done? and are they about to pave it? link

    when is phase 3 gonna be done? and are they about to pave it?

    finish bonnie brae asked 10 months ago

    On January 27th, Bonnie Brae at Airport Road was fully closed to all traffic. The contractor is working to complete all the underground improvements as well as paving of the section of Bonnie Brae between Airport Road and Main Stadium Drive to ensure this section of roadway can be open and accept traffic from TxDOT's 35E-Merge project which is now also under construction. Weather permitting, paving activities in this section will be complete and re-open to traffic in mid June 2025. 

    Paving activities for the remainder of south Bonnie Brae including the new alignment will occur in phases and are expected to begin Q3 2025.

    Currently, Phase 3 is anticipated to be fully complete in November 2026.

  • Share Is there any way to know when the construction will be finished enough for the buses to stop by our apartment again? My roommates and I live at Uptown apartments and we have no way of really knowing when the bus will come back to our stop or not so this is my last resort to try to find out. I assume the reason it hasn’t been able to get us yet is due to the lanes being closed, but I was wondering if this will be an issue for the entire school year? Or will we actually be able to take the bus sooner than later? Thanks. on Facebook Share Is there any way to know when the construction will be finished enough for the buses to stop by our apartment again? My roommates and I live at Uptown apartments and we have no way of really knowing when the bus will come back to our stop or not so this is my last resort to try to find out. I assume the reason it hasn’t been able to get us yet is due to the lanes being closed, but I was wondering if this will be an issue for the entire school year? Or will we actually be able to take the bus sooner than later? Thanks. on Twitter Share Is there any way to know when the construction will be finished enough for the buses to stop by our apartment again? My roommates and I live at Uptown apartments and we have no way of really knowing when the bus will come back to our stop or not so this is my last resort to try to find out. I assume the reason it hasn’t been able to get us yet is due to the lanes being closed, but I was wondering if this will be an issue for the entire school year? Or will we actually be able to take the bus sooner than later? Thanks. on Linkedin Email Is there any way to know when the construction will be finished enough for the buses to stop by our apartment again? My roommates and I live at Uptown apartments and we have no way of really knowing when the bus will come back to our stop or not so this is my last resort to try to find out. I assume the reason it hasn’t been able to get us yet is due to the lanes being closed, but I was wondering if this will be an issue for the entire school year? Or will we actually be able to take the bus sooner than later? Thanks. link

    Is there any way to know when the construction will be finished enough for the buses to stop by our apartment again? My roommates and I live at Uptown apartments and we have no way of really knowing when the bus will come back to our stop or not so this is my last resort to try to find out. I assume the reason it hasn’t been able to get us yet is due to the lanes being closed, but I was wondering if this will be an issue for the entire school year? Or will we actually be able to take the bus sooner than later? Thanks.

    B C asked about 1 year ago

    Good Morning.  I have reached out to DCTA who provided the below information:

    The stop closures mentioned are due to the construction and closures on Oak and Hickory as part of the DME substation project. The eastbound stops on Oak between I35 and Bonnie Brae have been re-opened as of Friday with the new traffic control phasing, but the westbound Oak stops remain closed until further notice. DCTA updates routes information as we are made aware of it, but we are not aware of the specific end date for the construction in this area at this time.  These closures specifically impact the North Texas (NT 121), Evening Off Campus (EOC196), and Connect 7 routes. 

     DCTA now provides updated detour maps on our Service Updates webpage as new information comes in and issues rider alerts when buses are delayed. Students may be directed to the Customer Service number (940-243-0077) for assistance. 

  • Share With all the construction on Bobbie Brea can you please repave from the UNT soccer fields south so people can drive on them better. Then when done digging north of soccer fields do the same. A lot of people use it . Thank you on Facebook Share With all the construction on Bobbie Brea can you please repave from the UNT soccer fields south so people can drive on them better. Then when done digging north of soccer fields do the same. A lot of people use it . Thank you on Twitter Share With all the construction on Bobbie Brea can you please repave from the UNT soccer fields south so people can drive on them better. Then when done digging north of soccer fields do the same. A lot of people use it . Thank you on Linkedin Email With all the construction on Bobbie Brea can you please repave from the UNT soccer fields south so people can drive on them better. Then when done digging north of soccer fields do the same. A lot of people use it . Thank you link

    With all the construction on Bobbie Brea can you please repave from the UNT soccer fields south so people can drive on them better. Then when done digging north of soccer fields do the same. A lot of people use it . Thank you

    Connie Kerr asked over 1 year ago

    Bonnie Brae Phase 3 between FM 1515/Airport Road and Roselawn Drive is currently in construction.  We are working on the underground utilities phase now and anticipate paving improvements to begin Q2 2025.   While under construction, the contractor will be performing pothole patching/street maintenance as needed.    Please see the project updates for Phase 3 for additional details.

  • Share Will sidewalks be constructed along Bonnie Brae near the UNT Athletic village? I feel it would be a missed opportunity to not install walkable infrastructure for students and residents on game days on Facebook Share Will sidewalks be constructed along Bonnie Brae near the UNT Athletic village? I feel it would be a missed opportunity to not install walkable infrastructure for students and residents on game days on Twitter Share Will sidewalks be constructed along Bonnie Brae near the UNT Athletic village? I feel it would be a missed opportunity to not install walkable infrastructure for students and residents on game days on Linkedin Email Will sidewalks be constructed along Bonnie Brae near the UNT Athletic village? I feel it would be a missed opportunity to not install walkable infrastructure for students and residents on game days link

    Will sidewalks be constructed along Bonnie Brae near the UNT Athletic village? I feel it would be a missed opportunity to not install walkable infrastructure for students and residents on game days

    Henry_Burvee asked over 1 year ago

    Good Morning Sir,

    Yes, from Airport Road to Parvin, 10-foot side paths will be installed on each side of the street.  From Parvin to Roselawn, a 10-foot sidepath on the southbound side and a 5- foot sidewalk on the northbound side of the street will be installed.

    Thank you for your inquiry.

    Robin Davis, PMP
    Project Manager
    Capital Projects

  • Share Is there any information available as to what is being constructed to the South of the Police Training Station on Bonnie Brae and Vintage Drive. My Mother lives in the Cambridge Brook Development which is at the top of the hill off of Bonnie Brae. Many thanks for any information. on Facebook Share Is there any information available as to what is being constructed to the South of the Police Training Station on Bonnie Brae and Vintage Drive. My Mother lives in the Cambridge Brook Development which is at the top of the hill off of Bonnie Brae. Many thanks for any information. on Twitter Share Is there any information available as to what is being constructed to the South of the Police Training Station on Bonnie Brae and Vintage Drive. My Mother lives in the Cambridge Brook Development which is at the top of the hill off of Bonnie Brae. Many thanks for any information. on Linkedin Email Is there any information available as to what is being constructed to the South of the Police Training Station on Bonnie Brae and Vintage Drive. My Mother lives in the Cambridge Brook Development which is at the top of the hill off of Bonnie Brae. Many thanks for any information. link

    Is there any information available as to what is being constructed to the South of the Police Training Station on Bonnie Brae and Vintage Drive. My Mother lives in the Cambridge Brook Development which is at the top of the hill off of Bonnie Brae. Many thanks for any information.

    Brenda Western asked over 1 year ago

    Good Morning Brenda,

    Since I need a little more information to answer to this, do you mind emailing me at robin.davis@cityofdenton.com please?

  • Share What is the Status of BB from vintage to 377? Will it be closed for sometime? on Facebook Share What is the Status of BB from vintage to 377? Will it be closed for sometime? on Twitter Share What is the Status of BB from vintage to 377? Will it be closed for sometime? on Linkedin Email What is the Status of BB from vintage to 377? Will it be closed for sometime? link

    What is the Status of BB from vintage to 377? Will it be closed for sometime?

    Eswaybar asked over 2 years ago

    Good morning, The section of Bonnie Brae near Vintage in question is actually a Water Utilities project and not part of the roadway Improvements.  The Weekly Street Closure Report shows the project to be closed from August 7 to August 18.

    The contact for the project is Jamie Bond.  You can reach him directly at jamie.bond@cityofdenton.com

    Thank you,

    Robin Davis, PMP
    Capital Projects