Dry Fork Sanitary Sewer
Installation of approximately 4,600 linear feet of 24-inch sewer main north of Highland Park at Bonnie Brae west to I-35W Frontage Road and south to Corbin Road will provide wastewater services to Southwest Denton Area residents.
Project Status
Project Location
Installation of approximately 4,600 linear feet of 24-inch sewer main north of Highland Park at Bonnie Brae west to I-35W Frontage Road and south to Corbin Road will provide wastewater services to Southwest Denton Area residents.
Project Status
Project Location
-
April Construction Update
Share April Construction Update on Facebook Share April Construction Update on Twitter Share April Construction Update on Linkedin Email April Construction Update linkConstruction currently in progress. Wastewater line being installed.
-
February Update
Share February Update on Facebook Share February Update on Twitter Share February Update on Linkedin Email February Update linkConstruction currently in progress. Clearing complete and wastewater line being installed.
-
December Construction Update
Share December Construction Update on Facebook Share December Construction Update on Twitter Share December Construction Update on Linkedin Email December Construction Update linkConstruction currently underway and wastewater line being installed.
-
November Construction Update
Share November Construction Update on Facebook Share November Construction Update on Twitter Share November Construction Update on Linkedin Email November Construction Update linkConstruction for the Dry Fork project will start late November.
Crews will be on site setting up stormwater pollution protection and cleaning area for construction.
-
Dry Fork Update
Share Dry Fork Update on Facebook Share Dry Fork Update on Twitter Share Dry Fork Update on Linkedin Email Dry Fork Update linkConstruction contract has been awarded to Wilson Contract Services.
Construction is scheduled to begin October 31, 2023.
-
Dry Fork Update
Share Dry Fork Update on Facebook Share Dry Fork Update on Twitter Share Dry Fork Update on Linkedin Email Dry Fork Update linkESTIMATED SCHEDULE OF PROJECT
Final Design/Advertise - Q3 2023
Construction Contract Award - Q3 2023
Construction - Q3 2023 - Q2 2024
Project Closeout - Q2 2024
-
Update for Dry Fork
Share Update for Dry Fork on Facebook Share Update for Dry Fork on Twitter Share Update for Dry Fork on Linkedin Email Update for Dry Fork linkESTIMATED SCHEDULE OF PROJECT
Final Design/Advertise - Q3 2023
Construction Contract Award - Q3 2023
Construction - Q3 2023 - Q3 2024
Project Closeout - Q4 2024
-
Update for Dry Fork
Share Update for Dry Fork on Facebook Share Update for Dry Fork on Twitter Share Update for Dry Fork on Linkedin Email Update for Dry Fork linkESTIMATED SCHEDULE OF PROJECT
Final Design/Advertise - Q2 2023
Construction Contract Award - Q3 2023
Construction - Q3 2023 - Q3 2024
Project Closeout - Q4 2024
-
Dry Fork Project Update
Share Dry Fork Project Update on Facebook Share Dry Fork Project Update on Twitter Share Dry Fork Project Update on Linkedin Email Dry Fork Project Update linkESTIMATED SCHEDULE OF PROJECT
Final Design/Advertise - Q2 2023
Construction Contract Award - Q3 2023
Construction - Q3 2023 - Q3 2024
Project Closeout - Q4 2024
-
Dry Fork Project Update
Share Dry Fork Project Update on Facebook Share Dry Fork Project Update on Twitter Share Dry Fork Project Update on Linkedin Email Dry Fork Project Update linkESTIMATED SCHEDULE OF PROJECT
Final Design/Advertise - Q2 2023
Construction Contract Award - Q3 2023
Construction - Q3 2023 - Q3 2024
Project Closeout - Q4 2024
Project Information
Estimated Project Cost: $3.7 million
Sponsoring Department:
Engineering Department / Wastewater Collections
Funding Source: Wastewater Collections
Project Location: West side of Bonnie Brae near Corbin Rd.