FM1515 (Airport Rd)

Share FM1515 (Airport Rd) on Facebook Share FM1515 (Airport Rd) on Twitter Share FM1515 (Airport Rd) on Linkedin Email FM1515 (Airport Rd) link

Water and Wastewater line relocation for TxDOT widening of Airport Road.

Water and Wastewater line relocation for TxDOT widening of Airport Road.

  • Bidding

    Share Bidding on Facebook Share Bidding on Twitter Share Bidding on Linkedin Email Bidding link

    Bidding is open. Working with TxDOT on the agreement

  • Going Out to Bid

    Share Going Out to Bid on Facebook Share Going Out to Bid on Twitter Share Going Out to Bid on Linkedin Email Going Out to Bid link

    This is using the pre-qualified list and will advertise for 30 days.

  • Nearing Bid Time

    Share Nearing Bid Time on Facebook Share Nearing Bid Time on Twitter Share Nearing Bid Time on Linkedin Email Nearing Bid Time link

    Continuing to get easements and working to get the bid out soon.

  • About to Bid Project

    Share About to Bid Project on Facebook Share About to Bid Project on Twitter Share About to Bid Project on Linkedin Email About to Bid Project link

    Needing (3) easements still. Positive movement on acquiring the easements. Moving to get the contract out to bid.

  • Easements & Design

    Share Easements & Design on Facebook Share Easements & Design on Twitter Share Easements & Design on Linkedin Email Easements & Design link

    Needing (3) easements for (1) crossing. We may evaluate if the project can be let without having these.

    Project is at 100%, waiting to seal plans until ready to put contract out to bid.

  • Between 90% & 100% Design

    Share Between 90% & 100% Design on Facebook Share Between 90% & 100% Design on Twitter Share Between 90% & 100% Design on Linkedin Email Between 90% & 100% Design link

    This project is between 90% and 100% Design. Working with TxDOT on the documentation needed as this is a reimbursable project. City Real Estate department is working on acquiring the needed easements.

  • 90% Design Completed

    Share 90% Design Completed on Facebook Share 90% Design Completed on Twitter Share 90% Design Completed on Linkedin Email 90% Design Completed link

    Working to get the easements needed and review of the 90% design.

  • 60% Design Completed

    Share 60% Design Completed on Facebook Share 60% Design Completed on Twitter Share 60% Design Completed on Linkedin Email 60% Design Completed link

    60% Completed on 5/2. Moving towards 90% design. TxDOT has reviewed the 60%, no conflicts identified.