Hickory Creek Interceptor

Share Hickory Creek Interceptor on Facebook Share Hickory Creek Interceptor on Twitter Share Hickory Creek Interceptor on Linkedin Email Hickory Creek Interceptor link
In the Beginning ...

Hickory Creek Interceptor (HCI) Capital Improvement Project Program is a multi-phased sanitary sewer project. The existing interceptor was installed in the 1980s. The new construction will add capacity and improve wastewater services to accommodate future growth projected to occur in the Hickory Creek Basin.

Hickory Creek Interceptor Phase 1&2 Project Status

HCI 1 & 2 includes the replacement of approximately 13,000 linear feet (2.46 miles) of 36, 42, 48 and 54-inch sewer mains along Hickory Creek from Fort Worth Drive (US 377) to I-35W. Construction is ongoing and the project is expected to be complete the first of the new year (2023)


Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Complete

Q1 '23


Hickory Creek Interceptor Phase 3 Project Status

HCI 3 will continue from HCI 1&2 to the north extending the planned improvements to upgrade the Hickory Creek Interceptor Corridor. Installation of approximately 9,700 LF of 30-inch sewer line with an improved alignment to replace the existing 12-inch sewer main and the rehabilitation of an existing 12-inch sewer line that crosses the creek. Utilities, THC, and TxDOT are clear.

The project has started advertising process. Staff evaluated the scope of the project and recommended using CSP (Competitive Sealed Proposal) instead of IFB (Invitation For Bid or “low bid”). CSP will allow staff to consider the contractor's staff, project workload, and history within our highly competitive market without price being the sole consideration.

Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Q1 '23 - Q1 '24

Q1 '24


* All dates are estimates and subject to change without notice.



Hickory Creek Interceptor (HCI) Capital Improvement Project Program is a multi-phased sanitary sewer project. The existing interceptor was installed in the 1980s. The new construction will add capacity and improve wastewater services to accommodate future growth projected to occur in the Hickory Creek Basin.

Hickory Creek Interceptor Phase 1&2 Project Status

HCI 1 & 2 includes the replacement of approximately 13,000 linear feet (2.46 miles) of 36, 42, 48 and 54-inch sewer mains along Hickory Creek from Fort Worth Drive (US 377) to I-35W. Construction is ongoing and the project is expected to be complete the first of the new year (2023)


Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Complete

Q1 '23


Hickory Creek Interceptor Phase 3 Project Status

HCI 3 will continue from HCI 1&2 to the north extending the planned improvements to upgrade the Hickory Creek Interceptor Corridor. Installation of approximately 9,700 LF of 30-inch sewer line with an improved alignment to replace the existing 12-inch sewer main and the rehabilitation of an existing 12-inch sewer line that crosses the creek. Utilities, THC, and TxDOT are clear.

The project has started advertising process. Staff evaluated the scope of the project and recommended using CSP (Competitive Sealed Proposal) instead of IFB (Invitation For Bid or “low bid”). CSP will allow staff to consider the contractor's staff, project workload, and history within our highly competitive market without price being the sole consideration.

Initiation

Planning & Design

Advertise,

Bid & Award

Construction

Closeout

Complete

Complete

Complete

Q1 '23 - Q1 '24

Q1 '24


* All dates are estimates and subject to change without notice.



  • Project Status Update 3/29/24

    Share Project Status Update 3/29/24 on Facebook Share Project Status Update 3/29/24 on Twitter Share Project Status Update 3/29/24 on Linkedin Email Project Status Update 3/29/24 link
    supporting image

    It's been a Good Friday. Construction is on schedule and you've likely been able to see some of the construction of the nearly 2-mile long Sanitary Sewer Interceptor as they have approached the crossing under Airport Road (FM 1515). We appreciate your support as we make continued progress to the finish line and wish you a Happy Easter weekend.

  • Project Status Update 3/2024

    Share Project Status Update 3/2024 on Facebook Share Project Status Update 3/2024 on Twitter Share Project Status Update 3/2024 on Linkedin Email Project Status Update 3/2024 link

    It's March - While we all lose an hour for the time change, celebrate St. Patrick's Day, and respond to the threats of March Showers, Wilson Contractor Services is continuing to make great progress! The bores and tunnels are complete and Wilson Contractor Services is continuing to lay pipe. And if the weather is favorable - they will continue to remain ahead of schedule.


  • Project Status Update 02/2024

    Share Project Status Update 02/2024 on Facebook Share Project Status Update 02/2024 on Twitter Share Project Status Update 02/2024 on Linkedin Email Project Status Update 02/2024 link
    supporting image

    Happy Valentines Day - If there's a project to LOVE, it's the Hickory Creek Interceptor Phase 3. Wilson Contractors Services continues to make excellent progress and is on schedule. The project is currently approaching FM 1515 (Airport Road) moving in a northwest direction. The section from Corbin Road south towards IH 35W is already in service. The work at FM 1515 will including boring under the highway. You will see construction activities but there should be very minimal impacts to traffic.



  • Project Status Update 01/2024

    Share Project Status Update 01/2024 on Facebook Share Project Status Update 01/2024 on Twitter Share Project Status Update 01/2024 on Linkedin Email Project Status Update 01/2024 link

    Hickory Creek Interceptor has been making excellent progress and is on schedule. The project is currently being installed from Corbin Road moving in a northwest direction towards FM 1515 (Airport Road). The section from Corbin Road south towards IH 35W is already in service.

  • Project Status Update 10/2023

    Share Project Status Update 10/2023 on Facebook Share Project Status Update 10/2023 on Twitter Share Project Status Update 10/2023 on Linkedin Email Project Status Update 10/2023 link
    supporting image

    It's perfect construction weather, FINALLY! And Hickory Creek Interceptor 3 Construction is taking advantage of the cooler weather and making GREAT progress. There's not much to share other than Keep Up the GREAT Work....and Happy Halloween.

  • Project Status Update 8/2023

    Share Project Status Update 8/2023 on Facebook Share Project Status Update 8/2023 on Twitter Share Project Status Update 8/2023 on Linkedin Email Project Status Update 8/2023 link

    Welcome to the Hickory Creek Interceptor Phase 3 (HCI 3) project update. HCI 3 is a sanitary sewer interceptor that will replace approximately 9,700 LF (1.8 mi) of 30-inch sewer line from the northern termination of HCI 1&2 near IH 35 and continue north. It will also replace an existing 12-inch sewer main and rehabilitate an existing 12-inch creek crossing. The project was designed by the City's Engineering Department and the construction contract was awarded to Wilson Contractor Services, a local Denton contractor! The Notice to Proceed was issued Summer 2023 and is expected to be complete in Fall 2024. The contractor is currently securing the long-lead materials and once final delivery is made, clearing/grading, and installation will be ready.




  • FINAL HCI 1&2 Project Status Update & HCI 3 Kick Off

    Share FINAL HCI 1&2 Project Status Update & HCI 3 Kick Off on Facebook Share FINAL HCI 1&2 Project Status Update & HCI 3 Kick Off on Twitter Share FINAL HCI 1&2 Project Status Update & HCI 3 Kick Off on Linkedin Email FINAL HCI 1&2 Project Status Update & HCI 3 Kick Off link

    Hickory Creek Interceptor Phases 1&2 have been in operation and the key, as seen below, has literally been handed over to the City! The project was a success with Mountain Cascade of Texas performing the work, the City of Denton Utilities Department being in close contact and always available to help with unforeseen field issues, and the great teamwork of the City of Denton's Public Works Inspectors & Project Managers. Meanwhile, Hickory Creek Interceptor Phase 3 has been issued the Notice to Proceed with construction starting June 20, 2023, so look for Wilson Contractor Services to begin working in the area very soon!

  • Project Status Update 4/2023

    Share Project Status Update 4/2023 on Facebook Share Project Status Update 4/2023 on Twitter Share Project Status Update 4/2023 on Linkedin Email Project Status Update 4/2023 link
    supporting image

    The Easter Bunny was hiding eggs and you might be wondering - did all the contractors go in hiding, too? It's so quiet out here! Are they done?

    The HCI 1&2 sewer line is in service but the project is not what we call "CLOSED OUT." There's a little bit of pavement repair and vegetation needed so you still may see Mountain Cascade working in the area as they wrap up the final touches.

    The HCI 3 construction has not yet started construction. Behind-the-scenes office work is being coordinated such as getting the material approved and ordered. We anticipate Wilson Contractor Services will start construction around JUNE 1, 2023. Construction is expected to take 400 calendar days (weather dependent). For more information - join the Virtual Community Meeting that is scheduled for Thursday 4/20/23 at 6:00 pm.

  • Project Status Update 3/2023

    Share Project Status Update 3/2023 on Facebook Share Project Status Update 3/2023 on Twitter Share Project Status Update 3/2023 on Linkedin Email Project Status Update 3/2023 link
    supporting image

    Stay Tuned - We'll be picking up Speed in April.

    Meanwhile, Enjoy Saint Patrick's Day, March Madness, and the TIME CHANGE!

  • Project Status Update 2/2023

    Share Project Status Update 2/2023 on Facebook Share Project Status Update 2/2023 on Twitter Share Project Status Update 2/2023 on Linkedin Email Project Status Update 2/2023 link
    supporting image

    January 2023 accomplishment included the substantial completion of HCI 1&2. The remaining items include some pavement and vegetation restoration. For HCI 3, City of Denton Council awarded the Construction Contract to Wilson Contractor Services (Denton). February is starting icy and very cold but hey, it's Texas we'll warm up for Valentine's because Denton Loves Construction! Planned February tasks include wrapping up final paperwork to execute the contracts, setting a Public Meeting date, setting a Pre-Construction Meeting date. The Team will also be working to identify a Notice-to-Proceed (NTP) date and from that date, the project is anticipated to last 400 days (13 months) pending no issues (such as weather or unforeseen conflicts).