The team will conduct 60% plan review and approval.
October 30 2023
90% Plan Review
They team will review and approve 90% plans. We are getting close to construction.
January 30 2024
100% Plans Completed
Team, has completed 100% plans.
March 08 → April 07 2024
Bid/Award
We are opening the project for contractors to bid on March 8th, 2024. The project will advertised for a total of 30 days. The contractors who can bid on the project are from a pre-qualified list to ensure the project goes smoothly.