Utility Relocation Frontage Road at Fort Worth Drive

Share Utility Relocation Frontage Road at Fort Worth Drive on Facebook Share Utility Relocation Frontage Road at Fort Worth Drive on Twitter Share Utility Relocation Frontage Road at Fort Worth Drive on Linkedin Email Utility Relocation Frontage Road at Fort Worth Drive link

The Texas Department of Transportation (TxDOT) is widening Interstate Highway 35 (I-35) with an estimated construction start in September 2024. The I-35 Utility Relocation on the Frontage Road at Fort Worth Drive Project will move public utilities in support of TxDOT I-35 widening project with the relocation of 2,000 linear feet of water lines. This project is scheduled for 120 days of construction and is estimated to be completed in 2nd quarter 2024. Since the project is a forced relocation of City of Denton utilities, there will be reimbursements from TxDOT to support this effort at 100%.

The Texas Department of Transportation (TxDOT) is widening Interstate Highway 35 (I-35) with an estimated construction start in September 2024. The I-35 Utility Relocation on the Frontage Road at Fort Worth Drive Project will move public utilities in support of TxDOT I-35 widening project with the relocation of 2,000 linear feet of water lines. This project is scheduled for 120 days of construction and is estimated to be completed in 2nd quarter 2024. Since the project is a forced relocation of City of Denton utilities, there will be reimbursements from TxDOT to support this effort at 100%.

  • Acquiring Right of Way

    Share Acquiring Right of Way on Facebook Share Acquiring Right of Way on Twitter Share Acquiring Right of Way on Linkedin Email Acquiring Right of Way link

    Project is on schedule and we are now acquiring easements. Once we have all the easements we will begin the Bid/Award process.

  • Project is ready for bid!

    Share Project is ready for bid! on Facebook Share Project is ready for bid! on Twitter Share Project is ready for bid! on Linkedin Email Project is ready for bid! link

    All aspect of planning are complete. We are only waiting on one easement to close. Once said easement is closed we will move to the bid award phase.

  • Plan Review Complete!

    Share Plan Review Complete! on Facebook Share Plan Review Complete! on Twitter Share Plan Review Complete! on Linkedin Email Plan Review Complete! link
    supporting image

    60% plan review complete and approved. 90% plans will be ready for review at the end of October. Great job City Staff!

  • Planning Update

    Share Planning Update on Facebook Share Planning Update on Twitter Share Planning Update on Linkedin Email Planning Update link
    supporting image

    30% plan review is complete.