Phase 2 of the Mayhill project is currently in the final stage of design with right-of-way acquisitions underway, and is tentatively scheduled to begin construction in Q2 2021. This phase of the project will include a 4-lane expansion towards Colorado Boulevard. This phase will also address congestion issues and include a bridge over the DCTA Rail to eliminate the at-grade intersection with the DCTA Railroad.