Project Status Update 9/2023
Past and Present Activities
Earthwork (Excavation & Embankment & Road Prep)
Drainage (Storm Sewer, Regional Detention Facility)
Bridge Structures (Columns, Bents, Abutments, Caps)
Upcoming Construction*
Concrete Batch Plant: Set up Starts 10/2/23 thru 10/6/23
Paving: Starts 10/9/23 thru 11/10/23
Night-time Work (Bridge): 10/16/23 thru 11/3/23
(Bridge Beams 10/16 thru 10/22, Panels 10/23-11/3)
Weekend Work (Day time): 10/14/23 & 10/15/23 Hang Beams
Bridge Deck Panels/Pour: 11/6/23 thru 12/8/23
* All Dates are subject to change without notice