Project Status Update 9/2023

Past and Present Activities

Earthwork (Excavation & Embankment & Road Prep)

Drainage (Storm Sewer, Regional Detention Facility)

Bridge Structures (Columns, Bents, Abutments, Caps)

Upcoming Construction*

Concrete Batch Plant: Set up Starts 10/2/23 thru 10/6/23

Paving: Starts 10/9/23 thru 11/10/23

Night-time Work (Bridge): 10/16/23 thru 11/3/23

(Bridge Beams 10/16 thru 10/22, Panels 10/23-11/3)

Weekend Work (Day time): 10/14/23 & 10/15/23 Hang Beams

Bridge Deck Panels/Pour: 11/6/23 thru 12/8/23


* All Dates are subject to change without notice