Milam Creek Gravity Sewer and Lift Station

Share Milam Creek Gravity Sewer and Lift Station on Facebook Share Milam Creek Gravity Sewer and Lift Station on Twitter Share Milam Creek Gravity Sewer and Lift Station on Linkedin Email Milam Creek Gravity Sewer and Lift Station link

The Milam Creek Project is one of the final stages of the I-35 corridor utility relocation efforts. The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road. This effort will not only support TxDOT's I-35 widening it was also designed/upgraded to support future development in the area.

The Milam Creek Project is one of the final stages of the I-35 corridor utility relocation efforts. The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road. This effort will not only support TxDOT's I-35 widening it was also designed/upgraded to support future development in the area.

  • PUB & Council Set

    Share PUB & Council Set on Facebook Share PUB & Council Set on Twitter Share PUB & Council Set on Linkedin Email PUB & Council Set link

    PUB 4/15 & Council 4/16.

  • Moving to PUB & Council

    Share Moving to PUB & Council on Facebook Share Moving to PUB & Council on Twitter Share Moving to PUB & Council on Linkedin Email Moving to PUB & Council link

    PUB & Council later this Month with Contract Award around the corner.

  • Bidding Opening this Month

    Share Bidding Opening this Month on Facebook Share Bidding Opening this Month on Twitter Share Bidding Opening this Month on Linkedin Email Bidding Opening this Month link

    Bidding will open this month for 30 days. Still pending easements that impact the entire project.

  • Moving Forward towards Solicitation

    Share Moving Forward towards Solicitation on Facebook Share Moving Forward towards Solicitation on Twitter Share Moving Forward towards Solicitation on Linkedin Email Moving Forward towards Solicitation link

    We have received positive movement on acquiring needed easements to let half of the project.

  • Update on Easements

    Share Update on Easements on Facebook Share Update on Easements on Twitter Share Update on Easements on Linkedin Email Update on Easements link

    Discussions continue to resolve issues with property owners to acquire the easements needed. One is not responsive to the Cities' offers and another is wanting to be paid for future items with no guarantees of the work to be completed.

  • Easement Updates

    Share Easement Updates on Facebook Share Easement Updates on Twitter Share Easement Updates on Linkedin Email Easement Updates link

    The City is still talking with property owners to acquire the needed easements. (1) Owner is in good communication with the City. (1) Owner has countered the City's offer. (2) Owners are refusing to give easements.

  • Easements Still needed

    Share Easements Still needed on Facebook Share Easements Still needed on Twitter Share Easements Still needed on Linkedin Email Easements Still needed link

    City of Denton and it's authorized representatives are working diligently to get these easements.

  • Movement on Easements

    Share Movement on Easements on Facebook Share Movement on Easements on Twitter Share Movement on Easements on Linkedin Email Movement on Easements link

    Majority of the easements are being worked. Potential to split the project if the remaining easements are not acquired in a timely manner.

  • Awaiting Easements

    Share Awaiting Easements on Facebook Share Awaiting Easements on Twitter Share Awaiting Easements on Linkedin Email Awaiting Easements link

    Several property owners are not willing to give easements to the City. The City continues to reach out to property owners to reach settlement to move the project forward.

  • Offer Letters Have Been Sent

    Share Offer Letters Have Been Sent on Facebook Share Offer Letters Have Been Sent on Twitter Share Offer Letters Have Been Sent on Linkedin Email Offer Letters Have Been Sent link

    Offer letters have been sent to landowners. Hopefully, soon we can close negotiations and move the project forward.

Page last updated: 04 Apr 2025, 08:35 AM