Milam Creek Gravity Sewer and Lift Station

Share Milam Creek Gravity Sewer and Lift Station on Facebook Share Milam Creek Gravity Sewer and Lift Station on Twitter Share Milam Creek Gravity Sewer and Lift Station on Linkedin Email Milam Creek Gravity Sewer and Lift Station link

The Milam Creek Project is one of the final stages of the I-35 corridor utility relocation efforts. The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road. This effort will not only support TxDOT's I-35 widening it was also designed/upgraded to support future development in the area.

The Milam Creek Project is one of the final stages of the I-35 corridor utility relocation efforts. The project will relocate and add wastewater lines between Highway 77 and Ganzer Road. In addition, a new lift station will be constructed at the intersection of Ganzer Road and East I-35 Frontage Road. This effort will not only support TxDOT's I-35 widening it was also designed/upgraded to support future development in the area.

  • ROW negotiations still in progress

    Share ROW negotiations still in progress on Facebook Share ROW negotiations still in progress on Twitter Share ROW negotiations still in progress on Linkedin Email ROW negotiations still in progress link
    supporting image

    Due to the complexity of the right of ways and the scale of the project, this process is taking longer than expected. All easements have been created and offers have been sent. Thank you all for your patience.

  • Right of Way Acquisition

    Share Right of Way Acquisition on Facebook Share Right of Way Acquisition on Twitter Share Right of Way Acquisition on Linkedin Email Right of Way Acquisition link

    All planning and design are complete. We are now obtaining easements and right of ways. Once, we've completed that we will begin the bid/award process.

  • Planning and Design Complete!

    Share Planning and Design Complete! on Facebook Share Planning and Design Complete! on Twitter Share Planning and Design Complete! on Linkedin Email Planning and Design Complete! link
    supporting image

    Our team has completed the planning and design! We are ready to begin the procurement process and conclude the easement acquisition phase.

  • Easement Acquisition

    Share Easement Acquisition on Facebook Share Easement Acquisition on Twitter Share Easement Acquisition on Linkedin Email Easement Acquisition link
    supporting image

    The team has been working hard on obtaining easements; once all easements have been obtained we will move forward with advertise and bid.

  • Design Review Update

    Share Design Review Update on Facebook Share Design Review Update on Twitter Share Design Review Update on Linkedin Email Design Review Update link

    The team just completed 90% design review and approval; 100% plans are currently being drawn finalized.

Page last updated: 04 Apr 2025, 08:35 AM