This project consists of full depth reconstruction of 24 street segments within the NBHD-4 project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes replacing existing aging water and sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements, and street lighting. Following is a summary of key scope items:

  • Street Reconstruction – Approx. 8,700 linear feet
  • Public Water Line Replacement – Approx. 7,000 linear feet (including service connections)
  • Public Sanitary Sewer Line Replacement – Approx. 5,800 linear feet (including service connections)
  • Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development.
  • Sidewalks – Limited improvements as determined during design development
  • Streetlights – Limited improvements as determined by lighting study





The street segments include:

STREET SEGMENT

FROM

TO

STREET SEGMENT

FROM

TO

Brightwood

Wilsonwood Dr

Longfellow Ln

Dunes Pl

Dunes St

S Culdesac

Broken Arrow

Dunes St

Old Orchard Ln

Jamestown

Williamsburg Rw

Mistywood Ln

Broken Bow

Dunes St

Windsor Dr E

Jamestown

Maid Marion Pl

Williamsburg Rw

Broken Bow

Windsor Dr

North

Jamestown

Locksley Ln

Maid Marion Pl

Chaparral

Cooper Branch E

East

Maid Marian

Jamestown Ln

Locksley Ln

Churchill

Wellington Dr

Windsor Dr E

Mill Pond

Emerson Ln

Old North Rd

Churchill

Churchill Cr

Wellington Dr

Old Orchard

Dunes St

Broken Arrow Rd

Churchill

Churchill Cir

Churchill Dr

Old Orchard

Dunes St

S Culdesac

Churchill

Wellington Dr

Churchill Dr

Old Orchard

Windsor Dr E

Broken Arrow Rd

Dunes

Broken Bow Rd

Old Orchard Ln

Pickwick

Oxford Ct

Windsor Dr E

Dunes

Old Orchard Ln

Dunes Pl

Wellington

Churchill Cr

Heather Ln

Dunes

Dunes Pl

Broken Arrow Rd

Wellington

Churchill Cr

Churchill Dr

This project consists of full depth reconstruction of 24 street segments within the NBHD-4 project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes replacing existing aging water and sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements, and street lighting. Following is a summary of key scope items:

  • Street Reconstruction – Approx. 8,700 linear feet
  • Public Water Line Replacement – Approx. 7,000 linear feet (including service connections)
  • Public Sanitary Sewer Line Replacement – Approx. 5,800 linear feet (including service connections)
  • Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development.
  • Sidewalks – Limited improvements as determined during design development
  • Streetlights – Limited improvements as determined by lighting study





The street segments include:

STREET SEGMENT

FROM

TO

STREET SEGMENT

FROM

TO

Brightwood

Wilsonwood Dr

Longfellow Ln

Dunes Pl

Dunes St

S Culdesac

Broken Arrow

Dunes St

Old Orchard Ln

Jamestown

Williamsburg Rw

Mistywood Ln

Broken Bow

Dunes St

Windsor Dr E

Jamestown

Maid Marion Pl

Williamsburg Rw

Broken Bow

Windsor Dr

North

Jamestown

Locksley Ln

Maid Marion Pl

Chaparral

Cooper Branch E

East

Maid Marian

Jamestown Ln

Locksley Ln

Churchill

Wellington Dr

Windsor Dr E

Mill Pond

Emerson Ln

Old North Rd

Churchill

Churchill Cr

Wellington Dr

Old Orchard

Dunes St

Broken Arrow Rd

Churchill

Churchill Cir

Churchill Dr

Old Orchard

Dunes St

S Culdesac

Churchill

Wellington Dr

Churchill Dr

Old Orchard

Windsor Dr E

Broken Arrow Rd

Dunes

Broken Bow Rd

Old Orchard Ln

Pickwick

Oxford Ct

Windsor Dr E

Dunes

Old Orchard Ln

Dunes Pl

Wellington

Churchill Cr

Heather Ln

Dunes

Dunes Pl

Broken Arrow Rd

Wellington

Churchill Cr

Churchill Dr

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is currently ongoing on Jamestown Lane, Maid Marion Place, and Old Orchard Ln. with Broken Arrow Rd shortly following.

    Street reconstruction and placement of the base layer of asphalt is currently underway on Churchill Drive, Churchill Cir and Wellington Drive. The surface layer of asphalt is anticipated to be complete for Mill Pond Rd, Pickwick Ln and Wellington Dr, Churchill Dr and Churchill Cir in the coming weeks. Street reconstruction will begin on Jamestown Lane and Maid Marion Place in the coming weeks.

    Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is currently ongoing on Wellington Dr, Churchill Cir, Churchill Dr, Jamestown Lane & Maid Marion Place with Old Orchard shortly following.

    Street reconstruction and placement of the base layer of asphalt is currently underway on Chaparral Ct & Pickwick Ln & Mill Pond Rd with the top layer of asphalt shortly following. Street reconstruction will begin on Wellington Dr, Churchill Cir and Churchill Dr. in the coming weeks.

    Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is currently ongoing on Wellington Dr, Churchill Cir, Churchill Dr & Jamestown Lane with Maid Marion Place shortly following.

    Street reconstruction is currently underway on Chaparral Ct & Pickwick Ln with Mill Pond Rd shortly following.

    Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is still ongoing on Wellington Dr, Churchill Cir and Churchill Dr with Jamestown Lane & Maid Marion Place shortly following.

    Street reconstruction is currently underway on Brightwood Terrace with Chaparral Ct & Pickwick Ln shortly following.

    Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is still ongoing on Mill Pond Rd & Pickwick Ln with Wellington Dr, Churchill Cir and Churchill Dr shortly following.

    Street reconstruction is currently underway on Brightwood Terrace with Pickwick Ln shortly following.

    Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is still ongoing on Mill Pond Rd, Pickwick Ln & Chaparral Ct.

    Street reconstruction will begin at Brightwood Terrace in the coming weeks. Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is currently occurring on Mill Pond Rd with Wellington Dr, Churchill Cir and Churchill Dr shortly following. Anticipate crews in the area with changing traffic patterns.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is currently occurring on Pickwick Lane with Brightwood Terrace and Mill Pond Rd shortly following. Road closures and changing traffic patterns will exist during the construction process.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Utility work is currently occurring on Chaparral Court with Pickwick Lane shortly following. Road closures and changing traffic patterns will exist during the construction process.

  • Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Construction is anticipated to start on July 17, 2023 for the Neighborhood 4 Project.

    Expect to see crews in the area of Chaparral Court and Pickwick Lane along with road closures and changing traffic patterns.