Utility work is currently ongoing on Jamestown Lane, Maid Marion Place, and Old Orchard Ln. with Broken Arrow Rd shortly following.
Street reconstruction and placement of the base layer of asphalt is currently underway on Churchill Drive, Churchill Cir and Wellington Drive. The surface layer of asphalt is anticipated to be complete for Mill Pond Rd, Pickwick Ln and Wellington Dr, Churchill Dr and Churchill Cir in the coming weeks. Street reconstruction will begin on Jamestown Lane and Maid Marion Place in the coming weeks.
Anticipate crews in the area with changing traffic patterns.