This project consists of full depth reconstruction of 24 street segments within the NBHD-4 project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes replacing existing aging water and sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements, and street lighting. Following is a summary of key scope items:
Street Reconstruction – Approx. 8,700 linear feet
Public Water Line Replacement – Approx. 7,000 linear feet (including service connections)
Public Sanitary Sewer Line Replacement – Approx. 5,800 linear feet (including service connections)
Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development.
Sidewalks – Limited improvements as determined during design development
Streetlights – Limited improvements as determined by lighting study
The street segments include:
STREET SEGMENT
FROM
TO
STREET SEGMENT
FROM
TO
Brightwood
Wilsonwood Dr
Longfellow Ln
Dunes Pl
Dunes St
S Culdesac
Broken Arrow
Dunes St
Old Orchard Ln
Jamestown
Williamsburg Rw
Mistywood Ln
Broken Bow
Dunes St
Windsor Dr E
Jamestown
Maid Marion Pl
Williamsburg Rw
Broken Bow
Windsor Dr
North
Jamestown
Locksley Ln
Maid Marion Pl
Chaparral
Cooper Branch E
East
Maid Marian
Jamestown Ln
Locksley Ln
Churchill
Wellington Dr
Windsor Dr E
Mill Pond
Emerson Ln
Old North Rd
Churchill
Churchill Cr
Wellington Dr
Old Orchard
Dunes St
Broken Arrow Rd
Churchill
Churchill Cir
Churchill Dr
Old Orchard
Dunes St
S Culdesac
Churchill
Wellington Dr
Churchill Dr
Old Orchard
Windsor Dr E
Broken Arrow Rd
Dunes
Broken Bow Rd
Old Orchard Ln
Pickwick
Oxford Ct
Windsor Dr E
Dunes
Old Orchard Ln
Dunes Pl
Wellington
Churchill Cr
Heather Ln
Dunes
Dunes Pl
Broken Arrow Rd
Wellington
Churchill Cr
Churchill Dr
This project consists of full depth reconstruction of 24 street segments within the NBHD-4 project area. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes replacing existing aging water and sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements, and street lighting. Following is a summary of key scope items:
Street Reconstruction – Approx. 8,700 linear feet
Public Water Line Replacement – Approx. 7,000 linear feet (including service connections)
Public Sanitary Sewer Line Replacement – Approx. 5,800 linear feet (including service connections)
Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development.
Sidewalks – Limited improvements as determined during design development
Streetlights – Limited improvements as determined by lighting study
Share Neighborhood 4 Public Meeting for Construction Kickoff on FacebookShare Neighborhood 4 Public Meeting for Construction Kickoff on TwitterShare Neighborhood 4 Public Meeting for Construction Kickoff on LinkedinEmail Neighborhood 4 Public Meeting for Construction Kickoff link
The Construction Kickoff Public Meeting was held on June 22nd.
If you were unable to attend the meeting please click on the photo below to watch the recorded presentation.
Share Notice of Community Meeting on FacebookShare Notice of Community Meeting on TwitterShare Notice of Community Meeting on LinkedinEmail Notice of Community Meeting link
The City of Denton will hold a Virtual Community Meeting at 6pm on Thursday, June 22, regarding street improvements in the Neighborhood 4 area.
Share Project Update on FacebookShare Project Update on TwitterShare Project Update on LinkedinEmail Project Update link
The contract has been awarded to the contractor and the City will host a virtual community meeting. Once a date is selected for the virtual community meeting, a sign up link will be posted in another project update on this page.
Share Project Update on FacebookShare Project Update on TwitterShare Project Update on LinkedinEmail Project Update link
2019 Street Bond Neighborhood 4 project is on schedule to go to City Council on 5/2/23 to award the project to the construction contractor. Once approved, the construction schedule can be finalized including the start and finish date.