Neighborhood 5B & Oakland Drainage

Share Neighborhood 5B & Oakland Drainage on Facebook Share Neighborhood 5B & Oakland Drainage on Twitter Share Neighborhood 5B & Oakland Drainage on Linkedin Email Neighborhood 5B & Oakland Drainage link

This project consists of full depth reconstruction of 17 street segments within the NBHD-5B project area and the upgrade of drainage system under Oakland Street (Pecan Creek) with the installation of a new detention pond. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes replacing existing aging water and sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements, and street lighting.

  • Approx. 8,400 linear feet
  • Public Water Line Replacement – Approx. 4,900 linear feet (including service connections)
  • Public Sanitary Sewer Line Replacement – Approx. 2,715 linear feet
  • Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development.
  • Sidewalks – Limited improvements as determined during design development
  • Streetlights – Limited improvements as determined by lighting study




This project consists of full depth reconstruction of 17 street segments within the NBHD-5B project area and the upgrade of drainage system under Oakland Street (Pecan Creek) with the installation of a new detention pond. This includes road reconstruction with subgrade stabilization, asphalt paving, concrete curb and gutter, and driveway replacements (limited to driveways that are within the existing right-of-way). The project will adhere to a holistic approach aimed at limiting future construction disruptions by replacing other aging public infrastructure within the limits of the project area. This includes replacing existing aging water and sanitary sewer lines, select stormwater infrastructure, limited sidewalk improvements, and street lighting.

  • Approx. 8,400 linear feet
  • Public Water Line Replacement – Approx. 4,900 linear feet (including service connections)
  • Public Sanitary Sewer Line Replacement – Approx. 2,715 linear feet
  • Stormwater Infrastructure Replacement – Serious Stormwater Infrastructure deficiencies will be addressed during design development.
  • Sidewalks – Limited improvements as determined during design development
  • Streetlights – Limited improvements as determined by lighting study




  • September 2025 Update

    Share September 2025 Update on Facebook Share September 2025 Update on Twitter Share September 2025 Update on Linkedin Email September 2025 Update link

    Project is currently at 60% design with right of way acquisition to follow.

Page last updated: 24 Sep 2025, 08:03 AM