Street Reconstruction - Neighborhood 7A

Share on Facebook Share on Twitter Share on Linkedin Email this link

This project consists of water and wastewater improvements along with street reconstruction of multiple street sections. The segments include Bernard from Roselawn to Acme, Leslie from Willowood to Dudley, Oakwood from McCormick to dead end, Uland from Kendolph to Ave D., Wisteria, Azalea, and Camellia from Laurel to Parvin, Public Alleyways from Laurel to Parvin.


Project Status

Project Timeline Early 2023 - Early 2024*


*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction.
Estimated project timelines may change due to weather, contractor scheduling, among other factors, and will be updated as needed.

This project consists of water and wastewater improvements along with street reconstruction of multiple street sections. The segments include Bernard from Roselawn to Acme, Leslie from Willowood to Dudley, Oakwood from McCormick to dead end, Uland from Kendolph to Ave D., Wisteria, Azalea, and Camellia from Laurel to Parvin, Public Alleyways from Laurel to Parvin.


Project Status

Project Timeline Early 2023 - Early 2024*


*Estimated project phase timelines are listed for active or planned projects. The projects are the most recent tentative timelines. Project phase timelines include the year range of a project life cycle including at least four phases of construction: planning, design, advertise, bid and award, and construction.
Estimated project timelines may change due to weather, contractor scheduling, among other factors, and will be updated as needed.

  • April Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Denton Neighborhood 7A: The remainder of concrete work on Leslie St. has been completed. Leslie St. Asphalt placement has been completed crews are currently working on miscellaneous street housekeeping. Utility crews have completed both the water and sewer utilities on Oakwood. Site Excavation and Concrete flatwork has also been completed throughout Oakwood. Construction activities regarding excavation and paving have been completed at Camellia St. Currently Earthworks crew are working on Oakwood prepping for Asphalt placement. Landscaping and Sodding crews will begin laying sod along Leslie St and Bernard St.

  • February Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    • Denton Neighborhood 7A: Paving underway on Leslie St. Meanwhile, earthwork on Oakwood Dr is underway. The flatwork concrete crews continue forming and pouring the concrete curb and gutter and driveways on Oakwood and will begin the paving soon after those operations are complete.
  • January Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    • Denton Neighborhood 7A: Paving has completed on Bernard St, Leslie St to begin site excavation. Meanwhile, utility crews are continuing the sanitary sewer installation on Oakwood Dr and are finishing up the water line at Leslie St. The flatwork concrete crews continue forming and pouring the concrete curb and gutter and driveways on Bernard and will begin the sidewalk operations soon after those operations are complete.
  • November Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Denton Neighborhood 7A: The earthwork crews are continuing subgrade preparations and have begun placing flex base on Bernard St, once completed they will transition to Leslie St to begin site excavation. Meanwhile, utility crews are continuing the sanitary sewer installation on Oakwood Dr and are finishing up the water line at Leslie St. The flatwork concrete crews continue forming and pouring the concrete curb and gutter and driveways on Bernard and will begin the sidewalk operations soon after those operations are complete.

  • October Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    • Denton Neighborhood 7A: Underwood operations have been completed with the installation of the ribbon curb and placement of new asphalt. Earthwork crews have started subgrade preparations and have begun placing flex base on Bernard St. Simultaneously, flatwork concrete crews have commenced the curb and gutter on Bernard. Meanwhile, utility crews are finishing up the sanitary sewer install on Leslie St. and are preparing to tie in the new water line on Bernard St. Once Bernard St work is complete, utility crews will move to Oakwood Dr and begin underground utilities.
  • September Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    • Denton Neighborhood 7A: The earthwork crews have completed subgrade preparations and have placed asphalt on Wisteria St and the Alleys. Simultaneously, the flatwork concrete crews have completed the curb and gutter on Wisteria St and Alleys A, B, and C, and are currently backfilling the back of the curb in preparation for sod. Meanwhile, utility crews are finishing up the installation of sanitary sewer and water services on Bernard St. and are beginning on the sanitary sewer line on Leslie St.
  • August Construction Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    • Denton Neighborhood 7A: The earthwork crews have completed placing asphalt on Camelia St and Azalea St, and will finish preparing Wisteria St for upcoming asphalt paving. The flatwork concrete crews have completed curb and gutter on Azalea and Camelia, and are in the process of completing Wisteria St. Once complete with Wisteria, the earthwork and flatwork crews will mobilize to Alley A, B, and C. Meanwhile, utility crews continue the installation of domestic water and sanitary sewer lines along Bernard St.
  • July Update Neighborhood-7A

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image
    • Denton Neighborhood 7A: Utility crews continue installation of domestic water and sanitary sewer lines on Bernard St. The earthwork crews have completed placing asphalt on Camelia St and are currently preparing Azalea St and Wisteria St for upcoming asphalt paving. The flatwork concrete crews have mobilized to Camelia St and are continuing work on the curb and gutter.
  • June Update for NH-7A Project

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Denton Neighborhood 7A: Work is fully underway for the Neighborhood 7A project with a utility crew installing the domestic water line on Bernard St (Roselawn St to Parvin St) followed by the sanitary sewer line. The earthwork crew began roadway preparations along Camelia St, Azalea St, and Wisteria St in prep for asphalt paving in the coming weeks. Flatwork crews will begin shortly thereafter on curbs and gutters on Camelia St.

  • Update for Neighborhood 7A Project

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    Construction will start May 22, 2023 for the Neighborhood 7A Project

    Expect to see crews in the area along with road closures with changing traffic patterns.

    Detours will be provided for road closures.

Page last updated: 01 Apr 2024, 05:17 AM