August Construction Update
- Denton Neighborhood 7A: The earthwork crews have completed placing asphalt on Camelia St and Azalea St, and will finish preparing Wisteria St for upcoming asphalt paving. The flatwork concrete crews have completed curb and gutter on Azalea and Camelia, and are in the process of completing Wisteria St. Once complete with Wisteria, the earthwork and flatwork crews will mobilize to Alley A, B, and C. Meanwhile, utility crews continue the installation of domestic water and sanitary sewer lines along Bernard St.