- Denton Neighborhood 7A: Utility crews continue installation of domestic water and sanitary sewer lines on Bernard St. The earthwork crews have completed placing asphalt on Camelia St and are currently preparing Azalea St and Wisteria St for upcoming asphalt paving. The flatwork concrete crews have mobilized to Camelia St and are continuing work on the curb and gutter.