October Construction Update
- Denton Neighborhood 7A: Underwood operations have been completed with the installation of the ribbon curb and placement of new asphalt. Earthwork crews have started subgrade preparations and have begun placing flex base on Bernard St. Simultaneously, flatwork concrete crews have commenced the curb and gutter on Bernard. Meanwhile, utility crews are finishing up the sanitary sewer install on Leslie St. and are preparing to tie in the new water line on Bernard St. Once Bernard St work is complete, utility crews will move to Oakwood Dr and begin underground utilities.
Share October Construction Update on Facebook
Share October Construction Update on Twitter
Share October Construction Update on Linkedin
Email October Construction Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends