September Construction Update

  • Denton Neighborhood 7A: The earthwork crews have completed subgrade preparations and have placed asphalt on Wisteria St and the Alleys. Simultaneously, the flatwork concrete crews have completed the curb and gutter on Wisteria St and Alleys A, B, and C, and are currently backfilling the back of the curb in preparation for sod. Meanwhile, utility crews are finishing up the installation of sanitary sewer and water services on Bernard St. and are beginning on the sanitary sewer line on Leslie St.