August Update & Lookahead
1. Apollo Drive: Selene Dr. to Redstone Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation
2. Cactus Circle: Yucca Dr. to Cul-de-sac
- Utility work to include lowering existing water services found to be too shallow. (Some residents may experience brief service interruptions)
- Earthwork to include rough grading, lime stabilization, and fine grading
- Paving to include asphalt placement followed by the installation of curb and gutter, driveways and miscellaneous concrete
3. Huisache Street: Aspen Dr. to Yucca Dr.
- Installation of curb and gutter, driveways and miscellaneous concrete
4. Juno Lane: Atlas Dr. to Stuart Rd.
- Earthwork to include lime stabilization, fine grading
- Paving to include the installation of curb and gutter, driveways and miscellaneous concrete
5. Northridge Street: Hinkle Dr. to Bolivar St.
- Utility work consisting of sewer installation
6. Pershing Drive: Atlas Dr. to Stuart Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation and waterline installation
7. Selene Drive: Stuart Rd. to End
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
- Earthwork to include rough grading, and lime stabilization
8. Sheraton Road: Imperial Dr. to Sun Valley Dr. (Notifications to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
- Earthwork to include rough grading
9. Sunnydale Lane: Kings Row to Sun Valley Dr.
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, driveways and sidewalks
- Earthwork to include rough grading, lime stabilization, and fine grading
10. Yellowstone Place: Hercules Lane to Juno Ln.
- Earthwork to include lime stabilization, fine grading
- Paving to include the installation of curb and gutter, driveways and miscellaneous concrete
11. Redstone Road: Hercules Ln. End
- Atmos gas conflicts have this segment in a delay. City is awaiting Atmos's completion of relocating their existing utilities before the contractor can proceed with the proposed improvements.

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends