August Update & Lookahead
Updated as of 08-20-2025
NBHD 1B
- Cactus Circle: Yucca Dr. to Cul-de-sac – Lime placed 8/18. First lift Hot mixed Asphalt (HMA) tentatively scheduled for the end of August with concrete work to follow.
- Camelot Street: Hercules Ln. to Stuart Rd. – Roadway work complete. Awaiting favorable weather to place sod. No current presence on the road.
- Huisache Street: Aspen Dr. to Yucca Dr. – Concrete placements starting week of 8/25 following the completion of Juno Lane
- Juno Lane: Atlas Dr. to Stuart Rd. – Concrete construction underway and expected to finish within a week. Final Hot mixed Asphalt (HMA) lift tentatively scheduled for the end of August.
- Northridge Street: Hinkle Dr. to Bolivar St. – Sanitary sewer underway. Crew is finishing Line B (Mesquite to Carroll). Fiber relocation completed 8/18, work has started on Line A (Mesquite to Hinkle). Line C (Carroll to Bolivar) expected to start week of 8/25.
- Pershing Drive: Atlas Dr. to Stuart Rd. – Sanitary Sewer delayed for Atmos gas line conflicts. Sundt demobilizing this week 8/19.
- Redstone Road: Hercules Ln. End – Sanitary Sewer delayed for Atmos gas line conflicts. Sundt demobilizing this week 8/20.
- Selene Drive: Stuart Rd. to End – SS main complete. Crew actively installing Sanitary Sewer services. Crew will demobilize to Northridge next week
- Sheraton Road: Imperial Dr. to Sun Valley Dr. – Crew mobilized 8/19 to pothole and commence Sanitary Sewer main.
- Sunnydale Lane: Kings Row to Sun Valley Dr. – Sanitary Sewer underway. Estimated completion of main and services 9/10.
- Titan Trail: Hercules Ln. to Redstone Rd. – Saw cut scheduled for next week. First deliveries expected 9/12.
- Yellowstone Place: Hercules Lane to Juno Ln. – Hot mixed Asphalt (HMA) first lift placed. Roadway prepared for concrete works to start following Huisache St.
1. Apollo Drive: Selene Dr. to Redstone Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation
2. Cactus Circle: Yucca Dr. to Cul-de-sac
- Utility work to include lowering existing water services found to be too shallow. (Some residents may experience brief service interruptions)
- Earthwork to include rough grading, lime stabilization, and fine grading
- Paving to include asphalt placement followed by the installation of curb and gutter, driveways and miscellaneous concrete
3. Huisache Street: Aspen Dr. to Yucca Dr.
- Installation of curb and gutter, driveways and miscellaneous concrete
4. Juno Lane: Atlas Dr. to Stuart Rd.
- Earthwork to include lime stabilization, fine grading
- Paving to include the installation of curb and gutter, driveways and miscellaneous concrete
5. Northridge Street: Hinkle Dr. to Bolivar St.
- Utility work consisting of sewer installation
6. Pershing Drive: Atlas Dr. to Stuart Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation and waterline installation
7. Selene Drive: Stuart Rd. to End
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
- Earthwork to include rough grading, and lime stabilization
8. Sheraton Road: Imperial Dr. to Sun Valley Dr. (Notifications to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
- Earthwork to include rough grading
9. Sunnydale Lane: Kings Row to Sun Valley Dr.
- Utility work consisting of sewer installation
- Miscellaneous demolition to include the removal of asphalt, curb and gutter, driveways and sidewalks
- Earthwork to include rough grading, lime stabilization, and fine grading
10. Yellowstone Place: Hercules Lane to Juno Ln.
- Earthwork to include lime stabilization, fine grading
- Paving to include the installation of curb and gutter, driveways and miscellaneous concrete
11. Redstone Road: Hercules Ln. End
- Atmos gas conflicts have this segment in a delay. City is awaiting Atmos's completion of relocating their existing utilities before the contractor can proceed with the proposed improvements.