August Update & Lookahead

1. Apollo Drive: Selene Dr. to Redstone Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)

  • Utility work consisting of sewer installation

2. Cactus Circle: Yucca Dr. to Cul-de-sac

  • Utility work to include lowering existing water services found to be too shallow. (Some residents may experience brief service interruptions)
  • Earthwork to include rough grading, lime stabilization, and fine grading
  • Paving to include asphalt placement followed by the installation of curb and gutter, driveways and miscellaneous concrete

3. Huisache Street: Aspen Dr. to Yucca Dr.

  • Installation of curb and gutter, driveways and miscellaneous concrete

4. Juno Lane: Atlas Dr. to Stuart Rd.

  • Earthwork to include lime stabilization, fine grading
  • Paving to include the installation of curb and gutter, driveways and miscellaneous concrete

5. Northridge Street: Hinkle Dr. to Bolivar St.

  • Utility work consisting of sewer installation

6. Pershing Drive: Atlas Dr. to Stuart Rd. (Notices to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)

  • Utility work consisting of sewer installation and waterline installation

7. Selene Drive: Stuart Rd. to End

  • Utility work consisting of sewer installation
  • Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
  • Earthwork to include rough grading, and lime stabilization

8. Sheraton Road: Imperial Dr. to Sun Valley Dr. (Notifications to be made to residents a minimum 48 Hrs. in advance of road closure to thru traffic)

  • Utility work consisting of sewer installation
  • Miscellaneous demolition to include the removal of asphalt, curb and gutter, and driveways
  • Earthwork to include rough grading

9. Sunnydale Lane: Kings Row to Sun Valley Dr.

  • Utility work consisting of sewer installation
  • Miscellaneous demolition to include the removal of asphalt, curb and gutter, driveways and sidewalks
  • Earthwork to include rough grading, lime stabilization, and fine grading

10. Yellowstone Place: Hercules Lane to Juno Ln.

  • Earthwork to include lime stabilization, fine grading
  • Paving to include the installation of curb and gutter, driveways and miscellaneous concrete

11. Redstone Road: Hercules Ln. End

  • Atmos gas conflicts have this segment in a delay. City is awaiting Atmos's completion of relocating their existing utilities before the contractor can proceed with the proposed improvements.






Share August Update & Lookahead on Facebook Share August Update & Lookahead on Twitter Share August Update & Lookahead on Linkedin Email August Update & Lookahead link
#<Object:0x000000003d383780>